                          Project                   Performance Measure(s)                Department(s)
             Core   Stormwater Projects       Implement Projects That Mitigate   Public Works
             PS                               Flooding Concerns
             2.1.1
             Summary:
                                                               The Lower Johnson Maintenance Ramp and Erosion
             Stormwater Projects are funded through the Stormwater   Project and the Lower Johnson Creek Dredging project
             Utility Fee and are included in the annual capital budget as   both began construction.
             well as in the Comprehensive Stormwater Master Plan.
                                                               The Harvest Hills Phase 1 improvements are under FEMA
             Update:                                           review.  Utility relocations and easement acquisition are
             The 2023 Miscellaneous Stormwater Construction contract   under way.
             includes major maintenance of storm drainage
             infrastructure throughout the City. Construction has been   California Lane construction is complete on Duther Drive,
             completed at Matlock, Creede, Cold Springs Drive, Ivycrest   Devonshire Drive, Avonhill Drive, Canongate Drive,
             Trail, Powder Horn, Silkcrest, and Green Acres.        Westchester Drive, Norfolk Drive, and California Lane.
                                                               Construction continues in the Fox Hill Area.


             The projects listed below include major maintenance projects that began construction prior to FY 2024 as well as the
             planned FY 2024 construction projects. Project milestones listed in the table will be updated as they occur.

                                                                                              Linear Feet of
                    Stormwater Capital       Est. Bid   Actual Bid   Estimated   Actual
                                                                                             Pipes/Channels
                   Improvement Project        Date       Date    Completion   Completion
                                                                                               Constructed
              2023 Miscellaneous Stormwater   Oct. 2023   Oct. 2023   Jan. 2025           1,470 LF of Pipe/215 LF
              Construction                                                                      of Channel
              Lower Johnson Maintenance     Mar. 2024  Mar. 2024  Jan. 2025                       N/A
              Ramp and Erosion
              Lower Johnson Creek Dredging,   May 2024   May 2024   March 2025                    N/A
              Phase 2



             The projects listed below include major flood mitigation projects that began construction prior to FY 2024 as well as the
             planned FY 2024 construction projects. Project milestones listed in the table will be updated as they occur.

                                                                                                  Linear Feet of
                 Stormwater Capital    Structures   Est. Bid   Actual Bid   Estimated   Actual
                                                                                                 Pipes/Channels
                 Improvement Project    Protected   Date       Date     Completion   Completion
                                                                                                  Constructed
              California Ln. Drainage   60 (all   June 2022  Feb. 2023   Aug. 2025               8,295 LF of Pipe
              Improvements Phase 1     phases)
              Harvest Hills Drainage   47 (all    Aug. 2019
              Improvements Phase 1     phases)
              2020 Drainage Phase 1                                                              1,558 LF of
              (Glen Springs, Turner    5          Mar. 2023  Mar. 2023  Dec. 2023   June 2024    Pipe/392 LF of
              Warnell, and Storie)                                                               Channel











                                                             142