                             Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
                                        Objective 1: Plan and Implement Stormwater Projects
                          Project                   Performance Measure(s)                Department(s)
             Core   Airport South Drainage    Operating Cost Recovery           Transportation
             PS    Improvements
             2.1.2
             Summary:

             The Airport, in conjunction with TxDOT Aviation and City of Arlington Public Works, completed a drainage study in FY
             2022. The existing storm drain infrastructure has deficiencies in capacity on the south end of the airport. Model results
             indicate ponding to the south of the airfield during all storm events, with runoff overtopping Green Oaks Boulevard
             during the 25-year and 100-year storm events. Flooding in this region can be attributed to undersized pipes that convey
             runoff below the vehicle service roads, as well as the volume of the runoff directed to this outfall location. New,
             increased drainage infrastructure is needed to control stormwater and prevent future flooding from continuing to cause
             issues.

             Update:
             Drainage improvements are at 60% design and have been submitted to Planning and Development Services for review.
             The design had to be changed due to an increase of planned developed land pertaining to this drainage improvement.
             Airport stormwater was no longer able to be directly discharged into Fish Creek and 48-hour detention pond will now be
             constructed to delay the flow of water into Fish Creek.



              Airport South Drainage Improvements

               Consultant Selection for design


                       Design and Bid phase


                 Reimbursable Grant Exection


                     Drainage Improvements

                            Final Inspection


                                         02/23        11/23          01/24       07/24        10/24      12/24