Leverage Technology
Goal 1: Ensure Availability of Information, Programs, and City Services
Objective 2: Implement New Technology
Project Performance Measure(s) Department(s)
LT Enterprise IT Project (FY 2023) – Project Completion Information Technology and Public
1.2.5 PW Storm Drain Hydrology Works
Summary:
Estimated
Milestone Status
Public Works (PW) has identified the Bentley OpenFlows Completion
rd
StormCAD and OpenFlows Flowmaster software as the Project Charter 3 Qtr. FY 2024 Completed
rd
solution they need to begin developing the level of service Planning Phase 3 Qtr. FY 2024 Completed
storm drain models. The consequence of failure analysis Procure Phase 4 Qtr. FY 2024 Completed
th
requires in-depth analysis of overland flow using a Design Phase 4 Qtr. FY 2024 Completed
th
software with 2D hydraulic modeling capability. The 2D Implementation Phase 4 Qtr. FY 2024 Completed
th
modeling software identified for evaluation include Project Closure 1 Qtr. FY 2025 Pending
st
Innovyze, InfoWorks ICM and XPSWMM software
packages.
This project will use PW’s business requirements to
validate that Bentley OpenFlow StormCAD and OpenFlow
Flowmaster, XPSWMM and InfoWorks ICM will meet their
needs, and use the City’s purchasing process to obtain the
necessary software.
Update:
The project team has installed the modeling software on
(1) one computer, and the other license remains
unassigned. Our project team is planning for project
closure activities.