Page 436 - FY 2025 Adopted Operating Budget and Business Plan
P. 436

Return to Table of Contents




                                               Leverage Technology

                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                             Objective 2: Implement New Technology
                           Project                  Performance Measure(s)               Department(s)
             LT    Enterprise IT Project (FY 2022) –   Project Completion     Information Technology and Police
             1.2.4  Electronic Dashboards for Police
             Summary:
                                                                                      Estimated
                                                                   Milestone                          Status
             This project will identify and acquire a solution that will             Completion
             ingest/analyze data from the sources listed above and   Project Charter   3  Qtr. FY 2022   Complete
                                                                                    rd
             others to provide dashboards and reporting tools to   Planning Phase   3  Qtr. FY 2022   Complete
                                                                                    rd
             APD. This solution will:                         Procure Phase        1  Qtr. FY 2023   Complete
                                                                                    st
                                                                                    nd
                                                              Design Phase         2  Qtr. FY 2023   Complete
                 •  Connect to multiple active data sources   Implementation Phases:
                 •  Monitor data sources and provide alerts     1. PS Analytics (No  2  Qtr. FY 2023   Complete
                                                                                    nd
                 •  End-user friendly allowing simple configuration  CAD)
                    of dashboards, and                          2. PS Analytics (w/  3  Qtr. FY 2023   Complete
                                                                                    rd
                 •  Allow for separation of APD data from City   CAD)
                    data.                                       3. EDP (w/ CJI Data)  4  Qtr. FY 2023   Complete
                                                                                    th
                                                                                    th
                                                                4. EDP Expansion   4  Qtr. FY 2024   In Progress
             APD is a client of Tyler Technologies utilizing their   Project Closure   1  Qtr. FY 2025
                                                                                    st
             Records Management System. During the pandemic,
             Tyler offered one of their projects, Socrata, to cities and   Note on Schedule Change:  There was a change order
             agencies free for dashboarding and tracking of COVID-  approved to extend the project schedule.
             19 issues (Tyler acquired Socrata – a data analytics and
             storage system in 2018). APD is in the process of
             implementing Socrata for use in their COVID-19 reports
             and dashboards.

             Update:
             Phase 4: The project team is working with the partner
             vendor to expand the utilization of the Enterprise Data
             Platform (EDP).


             The project team continues to evaluate the data
             filtering capabilities and verifying the data integrity, and
             the partner vendor is working on the issues identified.



























                                                             63