CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                     STOrM WATEr



                                City of Southlake FY 2022 CIP Project Status Form

                                             Drainage Basin Enhancements

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   Various Locations within the City

           PROJECT TIMELINE: Oct 2021  to  Sept 2026
           DESCRIPTION:
           Funding is requested for the implementation of recommendations from the storm water
           master plan focused on regional detention opportunities at strategic locations around
           the City.  The intent of this project is to allocate funds to purchase land or participate
           with developers to incorporate regional detention into future open space.







                                                                    New Request   Continuation Project  Partnership
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
           These funds allow the City to partner with developers to deliver Southlake 2030 Master  Public Health /      Rehab or Protection      Need / Service
                                                                    Safety
                                                                                  of Capital Stock
                                                                                                   Enhancement
           Plan recommendations and those being incorporated into 2035 Master Plan.
                                                                    2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                    Storm Water Master Plan
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           City will bear full cost of creating proposed regional detention facilities or expanding
           existing facilities.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Infrastructure, Partnership
           PROJECT #:  2022-48
                                                    EXPENDITURE SCHEDULE
             CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025     2026    UNFUNDED     TOTAL
              PLANNING / FEASIBILITY STUDY                                                             0
             ENGINEERING & DESIGN; TESTING                                                             0
                 LAND & ROW ACQUISITION                                                                0
           LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                      CONSTRUCTION  300,000  50,000  50,000   50,000   50,000   50,000    50,000     600,000
                       CONTINGENCY                                                                     0
                          TOTAL  300,000   50,000    50,000   50,000   50,000   50,000    50,000     600,000
                                                     OPERATIONAL IMPACT
           OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024     2025     2026    UNFUNDED     TOTAL
                   MAINTENANCE COSTS                                                                   0
                    PERSONNEL COSTS                                                                    0
                          TOTAL    0         0        0        0         0        0         0          0
                                                      FUNDING SCHEDULE
             CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024     2025     2026    UNFUNDED     TOTAL
                      GENERAL FUND                                                                     0
                           CEDC                                                                        0
                           CCPD                                                                        0
               PARK DEDICATION FEE FUND                                                                0
                     PUBLIC ART FUND                                                                   0
               ROADWAY IMPACT FEE FUND                                                                 0
              SANITARY SEWER IMPACT FEE                                                                0
                           SPDC                                                                        0
           STORMWATER UTILITY SYSTEM FUND  300,000  50,000  50,000  50,000  50,000  50,000  50,000   600,000
                          TIRZ #1                                                                      0
                       UTILITY FUND                                                                    0
                 WATER IMPACT FEE FUND                                                                 0
                          TOTAL  300,000   50,000    50,000   50,000   50,000   50,000    50,000     600,000
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
             CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                     TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1