CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                     STOrM WATEr



                                City of Southlake FY 2022 CIP Project Status Form

               Drainage Improvements at North Peytonville from 1330 North Peytonville to Post Oaks Creek

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   1330 North Peytonville to Post Oak Creek

           PROJECT TIMELINE: Oct 2025  to  Sept 2028
           DESCRIPTION:
           Funding is planned for engineering, design and construction for the drainage
           improvements between 1330 North Peytonville to Post Oaks Creek. Improvements   Project Location
           include installation of storm water lines, box culverts and curb inlets.








                                                                    New Request     Continuation Project  Partnership
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
           Improve drainage collection through storm sewer lines in order protect public     Public Health /   Rehab or Protection   Need / Service
                                                                    Safety
                                                                                  of Capital Stock
                                                                                                   Enhancement
           infrastructure and property during heavy storm events.
                                                                    2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                    Sustainability Master Plan - Objective 10.5
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Continuation of standing water after rain events.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Infrastructure
           PROJECT #:  2022-52
                                                    EXPENDITURE SCHEDULE
             CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025     2026    UNFUNDED     TOTAL
              PLANNING / FEASIBILITY STUDY  100,000                                                  100,000
             ENGINEERING & DESIGN; TESTING                   300,000                                 300,000
                 LAND & ROW ACQUISITION                               400,000   200,000              600,000
           LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                      CONSTRUCTION                                              750,000  2,400,000  3,150,000
                       CONTINGENCY                                                                     0
                          TOTAL  100,000     0        0      300,000  400,000   950,000  2,400,000  4,150,000
                                                     OPERATIONAL IMPACT
           OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024     2025     2026    UNFUNDED     TOTAL
                   MAINTENANCE COSTS  0      0        0        0         0        0       10,000     10,000
                    PERSONNEL COSTS                                                                    0
                          TOTAL    0         0        0        0         0        0       10,000     10,000
                                                      FUNDING SCHEDULE
             CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024     2025     2026    UNFUNDED     TOTAL
                      GENERAL FUND                                                                     0
                           CEDC                                                                        0
                           CCPD                                                                        0
               PARK DEDICATION FEE FUND                                                                0
                     PUBLIC ART FUND                                                                   0
               ROADWAY IMPACT FEE FUND                                                                 0
              SANITARY SEWER IMPACT FEE                                                                0
                           SPDC                                                                        0
           STORMWATER UTILITY SYSTEM FUND  450,000  0  0       0      500,000   800,000  2,400,000  4,150,000
                          TIRZ #1                                                                      0
                       UTILITY FUND                                                                    0
                 WATER IMPACT FEE FUND                                                                 0
                          TOTAL  450,000     0        0        0      500,000   800,000  2,400,000  4,150,000
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
             CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                     TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1

      456   FY 2022 City of Southlake  |  BUDGET BOOK
            WWW.CITYOFSOUTHLAKE.COM
   452   453   454   455   456   457   458   459   460   461   462