CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                        STOrM WATEr



                                   City of Southlake FY 2022 CIP Project Status Form

                                             Morgan Road Drainage Improvements

               DEPARTMENT: Public Works
               PROJECT
               LOCATION:  Morgan Rd and Cedar Ct

               PROJECT TIMELINE: Oct 2021  to  Sept 2024
               DESCRIPTION:
               Funding is requested to design and construct a drainage ditch, culvert and channel
               along Morgan Road. Due to the current slope and design, Maintenance has been
               performed multiple times throughout the past years. Field and drainage investigation
               has been performed to determine that the current system is best to be redesigned to
               prevent potential flooding damages to public and private property.







                                                                        New Request  Continuation Project  Partnership
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
               System is not working as efficiently as original design due to multiple iteration of  Public Health /      Rehab or Protection   Need / Service
                                                                       Safety
                                                                                     of Capital Stock
                                                                                                       Enhancement
               maintenance performed.
                                                                       2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                        Stormwater Master Plan
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               Continued sedimentation build-up will cause additional maintenance cost and
               manpower.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Infrastructure
               PROJECT #:  2022-47
                                                        EXPENDITURE SCHEDULE
                CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023     2024    2025      2026    UNFUNDED    TOTAL
                  PLANNING / FEASIBILITY STUDY                                                             0
                 ENGINEERING & DESIGN; TESTING  50,000                                                   50,000
                     LAND & ROW ACQUISITION                                                                0
               LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                          CONSTRUCTION                  250,000                                          250,000
                          CONTINGENCY                                                                      0
                              TOTAL    0       50,000   250,000    0        0         0         0        300,000
                                                         OPERATIONAL IMPACT
               OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024    2025      2026    UNFUNDED    TOTAL
                       MAINTENANCE COSTS                          1,000    1,000    1,000     1,000       4,000
                        PERSONNEL COSTS                                                                    0
                              TOTAL    0         0        0       1,000    1,000    1,000     1,000       4,000
                                                          FUNDING SCHEDULE
                 CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024    2025      2026    UNFUNDED    TOTAL
                          GENERAL FUND                                                                     0
                               CEDC                                                                        0
                               CCPD                                                                        0
                   PARK DEDICATION FEE FUND                                                                0
                         PUBLIC ART FUND                                                                   0
                   ROADWAY IMPACT FEE FUND                                                                 0
                  SANITARY SEWER IMPACT FEE                                                                0
                               SPDC                                                                        0
               STORMWATER UTILITY SYSTEM FUND  50,000   250,000                                          300,000
                              TIRZ #1                                                                      0
                           UTILITY FUND                                                                    0
                     WATER IMPACT FEE FUND                                                                 0
                              TOTAL    0       50,000   250,000    0        0         0         0        300,000
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
                CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1
                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  451