CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                        STOrM WATEr



                           Funding   Total Prior
             Project number                      FY 2022   FY 2023  FY 2024   FY 2025   FY 2026   Beyond     Total
                           Source     Funding

            System Capacity   Funding provides staff and Council with resources to reimburse developers for the oversizing of storm water lines to meet the
            Improvements   requirements of the Southlake 2030 Water Master Plan in cases where the developer is not required to provide the ultimate size
            (Storm Water) -
            Future Projects  of the line to serve proposed developments.



                          Storm
            2022-49       Water Utility   $100,000  $50,000  $50,000  $50,000   $50,000   $50,000   $50,000   $400,000
                          System




                          Funding is planned for the design and construction of a new bridge along North White Chapel Boulevard over Kirkwood Creek
                          Branch.  The flood and feasibility studies for the permanent solution to span these branches are currently underway.  This section
            North White
            Chapel Bridge   of roadway flooded in May 2015 due to heavy rainfall and overflow from Lake Grapevine and was closed for approximately seven
                          weeks. The road was overtopped most recently in September 2018 and underwent six months of repair before reopening. The
            Replacement at   roadway was also closed in March 2020 due to flooding.
            Kirkwood Branch
            / South Kirkwood  The proposed funding plan assumes full City of Southlake funding for the project. However, the City is exploring funding
            Branch
                          partnership options that would lower the City’s portion of funding. If those partnerships are successful, future funding plans will
                          reflect only the City’s portion of the cost, showing a reduction from the current plan.

            2022-50c      Utility Fund       $0        $0   $150,000  $600,000      $0        $0        $0    $750,000

                          Storm
            2022-50c      Water Utility   $2,675,000   $0  $1,375,000 $1,500,000  $3,075,000  $0        $0   $8,625,000
                          System

                          Total        $2,675,000      $0  $1,525,000 $2,100,000  $3,075,000  $0        $0   $9,375,000



            Simmons
            Court Drainage  Funding is planned for the design and construction of gabions along Simmons Court in order to stop erosion and correct the
            Improvements/  exposure of City sanitary sewer lines.
            Erosion Control


                          Storm
            2022-51       Water Utility   $400,000     $0    $50,000  $300,000      $0        $0        $0    $750,000
                          System



            Drainage
            improvements at
            North Peytonville Funding is planned for engineering, design and construction for the drainage improvements between 1330 North Peytonville to
            from 1330 North  Post Oaks Creek. Improvements include installation of storm water lines, box culverts and curb inlets.
            Peytonville to
            Post Oaks Creek

                          Storm
            2022-52       Water Utility   $450,000     $0        $0       $0   $500,000  $800,000 $2,400,000  $4,150,000
                          System







                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  447