CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                               SEWEr



                                City of Southlake FY 2022 CIP Project Status Form

                                        8-inch Sewer Line in Basin S-03 South of SH 114

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   SH114 and Lake Wood Acres

           PROJECT TIMELINE:         to
           DESCRIPTION:
           Funding is planned for right-of-way, engineering design, and construction of an 8-inch
           sanitary sewer line to provide service to planned mixed-use developments along State
           Highway 114 and also provide service to properties in Basin S-03 currently on septic
           systems (Lake Wood Acres Subdivision).







                                                                    New Request     Continuation Project  Partnership
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                     Public Health /   Rehab or Protection   Need / Service
           Provide Sanitary Sewer services to future customers and to residents that are currently  Safety  of Capital Stock  Enhancement
           on an on site septic system.
                                                                     2030/2035 COMPREHENSIVE PLAN? If yes, include ref:
                                                                    Waste Water System Master Plan #6 -WWS19- Tier 2
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Residents remain on septic systems, delayed development or private septic systems.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Infrastructure
           PROJECT #:  2022-44
                                                    EXPENDITURE SCHEDULE
             CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025     2026    UNFUNDED     TOTAL
              PLANNING / FEASIBILITY STUDY                                                             0
             ENGINEERING & DESIGN; TESTING                                                75,000     75,000
                 LAND & ROW ACQUISITION                                                   100,000    100,000
           LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                      CONSTRUCTION                                                        375,000    375,000
                       CONTINGENCY                                                                     0
                          TOTAL    0         0        0        0         0        0       550,000    550,000
                                                     OPERATIONAL IMPACT
           OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024     2025     2026    UNFUNDED     TOTAL
                   MAINTENANCE COSTS  0      0        0        0         0        0        5,000      5,000
                    PERSONNEL COSTS                                                                    0
                          TOTAL    0         0        0        0         0        0        5,000      5,000
                                                      FUNDING SCHEDULE
             CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024     2025     2026    UNFUNDED     TOTAL
                      GENERAL FUND                                                                     0
                           CEDC                                                                        0
                           CCPD                                                                        0
               PARK DEDICATION FEE FUND                                                                0
                     PUBLIC ART FUND                                                                   0
               ROADWAY IMPACT FEE FUND                                                                 0
              SANITARY SEWER IMPACT FEE                                                                0
                           SPDC                                                                        0
           STORMWATER UTILITY SYSTEM FUND                                                              0
                          TIRZ #1                                                                      0
                       UTILITY FUND  0       0        0        0         0        0       550,000    550,000
                 WATER IMPACT FEE FUND                                                                 0
                          TOTAL    0         0        0        0         0        0       550,000    550,000
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
             CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                     TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1