Page 449 - Southlake FY22 Budget
P. 449
CAPITAL IMPROVEMENTS PROGRAM (CIP)
STOrM WATEr
Funding Total Prior
Project number FY 2022 FY 2023 FY 2024 FY 2025 FY 2026 Beyond Total
Source Funding
Dove Creek at Funding is planned for the design and construction of drainage improvements. The proposed improvements include the
North Carroll construction of five 10-foot x 7-foot box culverts, raise and replace the roadway, clear and grade the channel, and install channel
Avenue stabilization consisting of interlocking concrete blocks.
Storm
2022-53 Water Utility $0 $0 $0 $0 $500,000 $500,000 $750,000 $1,750,000
System
Big Bear 6 at Funding is planned for the design and construction of drainage improvements. The proposed improvements include the
East Continental construction of four additional 12-foot x 8-foot box culverts, raise and replace the roadway, and clear and grade the channel.
Boulevard
Storm
2022-54 Water Utility $0 $0 $0 $125,000 $100,000 $0 $0 $225,000
System
Big Bear 8 at Funding is planned for the design and construction of drainage improvements. The proposed improvements include the
West Continental construction of six additional 12-foot x 8-foot culverts, raise and replace the roadway, clear and grade the channel, and install
Boulevard channel stabilization.
Storm
2022-55 Water Utility $0 $0 $0 $250,000 $1,000,000 $0 $1,250,000
System
Funding is planned for the design and construction of drainage improvements at Dove Creek at East Dove Road. The proposed
Dove Creek at improvements include the construction of fifteen 10-foot x 7-foot box culverts, raise and replace the roadway, clear and grade the
East Dove Road channel, and install channel stabilization consisting of interlocking concrete blocks.
Storm
2022-56 Water Utility $0 $0 $0 $0 $0 $500,000 $2,000,000 $2,500,000
System
Stormwater Total $4,275,000 $2,850,000 $1,925,000 $2,625,000 $4,525,000 $2,900,000 $5,250,000 $24,350,000