CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                     STOrM WATEr



                                City of Southlake FY 2022 CIP Project Status Form

                               Gateway Lakes Park Drainage Improvements & Bridge Replacement

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   E Kirkwood Blvd and N Kimball Ave

           PROJECT TIMELINE: Oct 2021  to  Sept 2023
           DESCRIPTION:
           Funding is requested for the engineering and construction of drainage improvements in
           Gateway Lakes Park. One of the ponds in the Gateway Lakes Park is in danger of
           breaching due to significant erosion near the embankment and immediately
           downstream. The engineering tasks will include a drainage study to design a spillway
           for the pond, gabion channel armoring downstream and the replacement of two
           pedestrian bridges.






                                                                     New Request  Continuation Project  Partnership
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
           This project is necessary for emergency preparedness and to prevent damage to     Public Health /   Rehab or Protection      Need / Service
                                                                    Safety
                                                                                  of Capital Stock
                                                                                                   Enhancement
           downstream public and private land and facilities.
                                                                    2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                    Sustainability Master Plan - Objective 10.2
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Continued erosion could result to infrastructure damage.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Infrastructure, Safety
           PROJECT #:  2022-46c
                                                    EXPENDITURE SCHEDULE
             CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025     2026    UNFUNDED     TOTAL
              PLANNING / FEASIBILITY STUDY                                                             0
             ENGINEERING & DESIGN; TESTING  50,000                                                   50,000
                 LAND & ROW ACQUISITION                                                                0
           LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                      CONSTRUCTION        1,000,000                                                 1,000,000
                       CONTINGENCY                                                                     0
                          TOTAL   50,000  1,000,000   0        0         0        0         0       1,050,000
                                                     OPERATIONAL IMPACT
           OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024     2025     2026    UNFUNDED     TOTAL
                   MAINTENANCE COSTS                 500       500      500      500       500        2,500
                    PERSONNEL COSTS                                                                    0
                          TOTAL    0         0       500       500      500      500       500        2,500
                                                      FUNDING SCHEDULE
             CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024     2025     2026    UNFUNDED     TOTAL
                      GENERAL FUND                                                                     0
                           CEDC                                                                        0
                           CCPD                                                                        0
               PARK DEDICATION FEE FUND    250,000                                                   250,000
                     PUBLIC ART FUND                                                                   0
               ROADWAY IMPACT FEE FUND                                                                 0
              SANITARY SEWER IMPACT FEE                                                                0
                           SPDC                                                                        0
           STORMWATER UTILITY SYSTEM FUND  350,000  450,000                                          800,000
                          TIRZ #1                                                                      0
                       UTILITY FUND                                                                    0
                 WATER IMPACT FEE FUND                                                                 0
                          TOTAL  350,000   700,000    0        0         0        0         0       1,050,000
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
             CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                     TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1

      450   FY 2022 City of Southlake  |  BUDGET BOOK
            WWW.CITYOFSOUTHLAKE.COM
   446   447   448   449   450   451   452   453   454   455   456