CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                     STOrM WATEr



                                City of Southlake FY 2022 CIP Project Status Form

                                           Big Bear 6 at East Continental Blvd

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   E Continental Blvd

           PROJECT TIMELINE: Oct 2024  to  Sept 2026
           DESCRIPTION:
           Funding is planned for the design and construction of drainage improvements. The
           proposed improvements include the construction of four additional 12-foot x 8-foot box
           culverts, raise and replace the roadway, and clear and grade the channel.           Project Location








                                                                    New Request   Continuation Project  Partnership
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
           To improve channel capacity, raise roadway and make improvements around channel.     Public Health /   Rehab or Protection      Need / Service
                                                                    Safety
                                                                                  of Capital Stock
                                                                                                   Enhancement
                                                                    2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                    Storm Water Master Plan - #8 - Tier 2
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Flow will be restricted by existing channels and the deterioration of the area adjacent to
           the channel.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Infrastructure
           PROJECT #:  2022-54
                                                    EXPENDITURE SCHEDULE
             CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025     2026    UNFUNDED     TOTAL
              PLANNING / FEASIBILITY STUDY                                                             0
             ENGINEERING & DESIGN; TESTING                   100,000                                 100,000
                 LAND & ROW ACQUISITION                       25,000  100,000                        125,000
           LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                      CONSTRUCTION                                                                     0
                       CONTINGENCY                                                                     0
                          TOTAL    0         0        0      125,000  100,000     0         0        225,000
                                                     OPERATIONAL IMPACT
           OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024     2025     2026    UNFUNDED     TOTAL
                   MAINTENANCE COSTS  0      0        0        0         0      10,000    10,000     20,000
                    PERSONNEL COSTS                                                                    0
                          TOTAL    0         0        0        0         0      10,000    10,000     20,000
                                                      FUNDING SCHEDULE
             CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024     2025     2026    UNFUNDED     TOTAL
                      GENERAL FUND                                                                     0
                           CEDC                                                                        0
                           CCPD                                                                        0
               PARK DEDICATION FEE FUND                                                                0
                     PUBLIC ART FUND                                                                   0
               ROADWAY IMPACT FEE FUND                                                                 0
              SANITARY SEWER IMPACT FEE                                                                0
                           SPDC                                                                        0
           STORMWATER UTILITY SYSTEM FUND  0  0       0      125,000  100,000     0         0        225,000
                          TIRZ #1                                                                      0
                       UTILITY FUND                                                                    0
                 WATER IMPACT FEE FUND                                                                 0
                          TOTAL    0         0        0      125,000  100,000     0         0        225,000
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
             CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                     TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1

      458   FY 2022 City of Southlake  |  BUDGET BOOK
            WWW.CITYOFSOUTHLAKE.COM
   454   455   456   457   458   459   460   461   462   463   464