Summary:
Implementation of Talent Acquisition and Learning Milestone Delivery Actual Delivery
Management platforms. Date Date
Pre‐planning phase Mar. 2017 Complete
The Applicant Tracking System (ATS) and Learning Plan Phase Apr. 2017 Complete
Management System (LMS) will allow the Human ATS Implementation May 2017 Complete
Resources Department to enhance its service delivery to Start
both internal departments and external customers. ATS Go‐live Aug. 2017 Complete
Utilizing technology in the form of web‐based systems for LMS Implementation Sept. 2017 Complete
both applicant tracking and e‐Learning that will help Start
provide alternate, efficient, and cost‐effective means of LMS Go‐Live Nov. 2017 Complete
tracking applicants and delivering training. Archive Design and Dec. 2017 Complete
Build
Update: Archive Go‐live Jan. 2018 Complete
This project is complete. Perform project Feb. 2018 Complete
documentation and
closure