Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                             Objective 2: Implement New Technology
                        Project                  Performance Measure(s)           City Service Team (Department)
             PTW   Police Ticket Writer    Project Completion                 Strategic Support (IT) and Neighborhood
             1.2.2                                                            Services (Police)
             Summary:
                                                                    Milestone           Estimated     Actual
             The Police Ticket Writer will replace the existing                        Completion   Completion
             proprietary ticket writing system and provide   Contract Negotiation     Dec. 2016    Complete
             increased efficiencies throughout the ticketing   Vendor Discovery       Jan. 2017    Complete
             process, improved data integrity and enhanced   Project Planning         Feb. 2017    Complete
             tools for Officers in the field.               Application configuration   Mar. 2017   Complete
             This project will:                             Application and integration   May 2017   Complete
                    Evaluate current ticket writing systems   testing
                    Select and implement system that that best   Officer and Admin training   May 2017   Complete
                    meets current and future department     Readiness review and go‐live  May 2017   Complete
                    needs                                   planning
                    Train Officers and deploy to the field   Go‐live                 May 2017     Complete
                                                            Post‐live system support   July 2017   Complete
             Project completion is expected in the 3  quarter of   Decommission AutoCite   July 2017   Complete
                                             rd
             FY 2018.                                       Implement NLETS           July 2017    Complete
                                                            functionality
             Update:                                        Complete phase‐2          Feb. 2018    Complete
                       th
             During the 4  quarter, the historical Autocite   implementation of up to 25
             citations were migrated to the Brazos web portal   ticket writers
             and made available for reference purposes.     Perform additional 3 days of   Feb. 2018   Complete
             AutoCIte was fully decommissioned from the     training
             environment.                                   Migrate historical AutoCite   Sept. 2018   Complete
                                                            Citations to Brazos web
                                                            portal
                                                            Project Closeout          1  Qtr. 2019
                                                                                       st