Page 76 - CityofArlingtonFY26AdoptedBudget
P. 76

Business Plan




                             Preserve Financial Stability and Resilience
                                       Plan, Manage, and Maintain Public Assets

                      Project                   Performance Measure(s)                    Department(s)
             Northeast Library          • Overall Satisfaction of Project Management    Asset Management and Library
             Improvements               • Project Completion on Time and at Budget

             Summary:
             The Northeast Library at 1905 Brown Boulevard was      Milestone        Estimated     Actual
             built in 1995 and has many of its original building                    Completion    Completion
             components which are beyond projected service life. In
             May 2023, Arlington voters approved $1.1 million in
             general obligation bonds for needed improvements,
             including replacing the roof, windows, and window
             storefront entrance. Additionally, there are areas on the
             site where the concrete sidewalk has failed and no
             longer compliant with accessibility standards so that is
             also included in the project scope of work.


                             Preserve Financial Stability and Resilience


                                       Plan, Manage, and Maintain Public Assets
                         Project                     Performance Measure(s)                 Department(s)
             Police Evidence Storage, Crime Lab   • Overall Satisfaction of Project Management   Asset Management and Police
             & North District Substation     • Project Completion on Time and at Budget

             Summary:                                                                Estimated      Actual
             In November 2018, Arlington voters approved        Milestone           Completion    Completion
             general obligation bonds to design and build a   Initial Project      May 2021     Jan. 2022
             new Police Evidence Storage Facility. In Winter   Schedule/Development Phase
             of 2021, City Council approved the purchase of   Request for Qualifications for   June 2021    Feb. 2022
             a commercial property at 1715 E. Lamar Blvd.   Architect/Engineer
             This property will be converted into a new   Architect/Engineer Selection   Spring 2022    June 2022
             facility for the Police Department that will house   Process
             a North District substation, evidence storage   Council Approval of Architect   Spring 2022    June 2022
             and crime lab, and Code Compliance.        Contract
                                                        Design Phase               Summer 2023   Fall 2023
                                                        Finalize Construction      Fall 2023    Summer 2024
                                                        Documents
                                                        Permit Phase               Winter 2023    Summer 2024
                                                        Bidding Phase              Summer 2024   Feb. 2025

                                                        Construction Begins
                                                        Finalize Selection of Fixtures,
                                                        Furniture, and Equipment
                                                        Construction Complete