Page 74 - CityofArlingtonFY26AdoptedBudget
P. 74

Business Plan




                             Preserve Financial Stability and Resilience
                                       Plan, Manage, and Maintain Public Assets

                      Project                     Performance Measure(s)                   Department(s)
             Fire Station #8 Rebuild     • Overall Satisfaction of Project Management    Asset Management and Fire
                                        • Project Completion on Time and at Budget

             Summary:                                                                Estimated      Actual
             In November 2018, Arlington voters approved          Milestone          Completion   Completion
             general obligation bonds for the reconstruction of   Issue a Request for   Spring 2022    Spring 2022
             Fire Station #8. The Arlington Fire Department   Qualifications (RFQ) for
             has partnered with Asset Management to re-   Architects
             design the existing facility located at 2004   Select an Architect for Design   Summer 2022   Fall 2022
             Madison Drive. The station is at the north part of   Council Approval of Architect  Fall 2022    Fall 2022
             the City and built in 1978 and is currently   Contract
             managed by the Fire Department and was most   Design Phase             Summer 2023   Fall 2023
             recently remodeled in 2018.
                                                          Site Permit Phase         Summer 2023   Dec. 2023
                                                          Bidding Phase             Fall 2023    Summer 2024
                                                          Building Permit Phase     Summer 2023   Summer 2024
                                                          Construction Phase start    Fall 2024    Fall 2024
                                                          Move In                   Fall 2025




                             Preserve Financial Stability and Resilience

                                       Plan, Manage, and Maintain Public Assets
                      Project                   Performance Measure(s)                    Department(s)
             Library Facilities         • Overall Satisfaction of Project Management    Asset Management and Library
             Improvements               • Project Completion on Time and at Budget

             Summary:
             In May 2025, Arlington voters approved $2.4 million   Milestone        Estimated     Actual
             in general obligation bonds to replace various major                  Completion    Completion
             building components that are beyond projected
             service life at various library branches. These
             improvements will include replacement of
             windows/doors, roof, plumbing, Heating, Ventilation,
             and Air Conditioning (HVAC), electrical wiring, and
             lighting and fire alarm system equipment.