Business Plan




                             Preserve Financial Stability and Resilience
                                       Plan, Manage, and Maintain Public Assets

                      Project                   Performance Measure(s)                    Department(s)
             New Traffic Management     • Overall Satisfaction of Project Management    Asset Management and Public Works
             Center                     • Project Completion on Time and at Budget

             Summary:
             The City’s Traffic Management Center needs to          Milestone       Estimated      Actual
             relocate from the Ott Cribbs Public Safety Center into                Completion    Completion
             a larger space. The project goals include to identify,
             and if needed acquire, an existing building to remodel.
             The remodeled facility will house office space to
             include eight offices, 10 cubicle spaces, and 6-10
             workstations. Additionally, space would be made
             available for 30 workstations to accommodate field
             staff, including a conference room, a break room and
             work area. A server closet and back-up generator is
             also required for the facility. The target completion is
              st
             1  Quarter FY 2026 so that the center is operational
             by January or February 2026 in time for the World
             Cup.



                             Preserve Financial Stability and Resilience

                                       Plan, Manage, and Maintain Public Assets
                          Project                   Performance Measure(s)                Department(s)
             New York 2.5 Million Gallon (MG)   Construct the New York 2.5 MG EST   Water Utilities
             Elevated Storage Tank (EST)

             Summary:                                                                  Estimated     Actual
             Arlington Water Utilities (AWU) annually provides billions of   Milestone   Completion  Completion
             gallons of water to Arlington residents through more than   Design       July 2025
             1,400 miles of water mains and 10 elevated storage tanks.   Bidding Phase   Oct. 2025
             Optimal performance of the water storage and distribution   Construction   June 2027
             system is essential to providing safe drinking water. The
             construction of a new 2.5 million gallon elevated storage
             tank is required to maintain distribution system pressure,
             meet water demand, and meet storage requirements set by
             the Texas Commission on Environmental Quality (TCEQ).

             The New York 2.5 million gallon elevated storage tank will
             be constructed near the corner of New York Avenue and
             Craig Hanking Drive, adjacent to the East Arlington Police
             Service Center.