Put Technology to Work
Goal 1: Ensure Availability of Information, Programs, and City Services
Objective 2: Implement New Technology
Project Performance Measure(s) Department(s)
PTW SCADA Integrator Update Treatment Production Facilities – Water Utilities
1.2.2 SCADA
Summary:
Milestone Estimated Actual
As the Water Department Treatment Division is Completion Completion
substantially updating its production facilities over the PBWTP Hydrogen Nov. 2020 July 2021
next five years, the need for a comprehensive Supervisory Peroxide System
Control and Data Acquisition (SCADA) integration project SCADA Standards and June 2020 Dec. 2020
was identified. This project will set programming and Governance
hardware standards and modernize the Human Machine JKWTP Chemical Sept. 2022
Interface (HMI) platform utilized for all water treatment Project
operational processes. JKWTP Backwash May 2022
Improvements
PBWTP Chemical Sept. 2024
Clearwell and PS
Improvements
LARWPS Shared Nov. 2024
Operations
Improvements