                                             Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                         Objective 3: Increase Convenience for the Customer
                          Project                   Performance Measure(s)         City Service Team (Department)
             PYW   Enterprise IT Project (FY 2019)  Project Completion          Shared Services (IT) and Economic
             1.3.1  – Inspection Scheduling                                     Development and Capital Investment
                                                                                (Planning)
             Summary:
                                                                   Milestone          Target Date     Status
             Planning & Development Services (PDS) will      Charter Development    1  Qtr. FY 2019    Complete
                                                                                     st
             implement the Contractor Application (App) within   Project Planning   2  Qtr. FY 2019   Complete
                                                                                     nd
             the AMANDA Application.  The Contractor App will   Design / Develop    2  Qtr. FY 2020   Complete
                                                                                     nd
             allow builders and residents to utilize a mobile device   Implementation / Go Live  3  Qtr. FY 2021    Complete
                                                                                     rd
             to request and view permits, schedule and       Project Close          4  Qtr. FY 2021   Complete
                                                                                     th
             reschedule inspections, view status of
             permit/inspection requests, receive next‐in‐line   Note:
             notifications and results via text or email.   This project was delayed due to the decision to change direction
                                                           of the project from implementing the Contractor App. This
             The PDS project team, worked with the vendor,   scope change and the initial project delay due to resource
             Unisys, to define requirements to improve mobile   constraints have caused delays since the project Charter was
             device functionality for AP.COM.  Unisys will develop   signed in 2019.
             these improvements to mobile device functionality
             for AP.COM.

             Update:
             The project team completed all remaining tasks and
             closed the project.