CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                     WATEr



                                   City of Southlake FY 2022 CIP Project Status Form

                               Water and Wastewater System Risk and Resiliency Improvements (AWIA/SB3)

              DEPARTMENT: Public Works
              PROJECT
              LOCATION:   Citywide

              PROJECT TIMELINE: Oct 21  to  Sept 22
              DESCRIPTION:
               The American Water Infrastructure Act (AWIA) requires community water systems
               serving more than 3,300 people to develop or update risk assessments and
               emergency response plans (ERPs). The law specifies the components that the risk
               assessments and ERPs must address, and establishes deadlines by which water
               systems must certify to the Environmental Protection Agency (EPA) the completion of
               the risk assessment and ERP. Southlake's risk assessment and ERP will be complete
               no later than December 2021, in accordance with the law. This requested funding is to
               support initial engineering service requirements to meet these standards. Future
               projects will be identified and programmed as part of future capital projects or
               operational funds. In addition, the 87th State of Texas Legislature passed SB3 which
               overlays requirements on water utilities related to emergency preparedness and
               planning. This request will establish a fund to address the most critical items as
               prioritized by both AWIA and SB3 requirements.           New Request  Continuation Project  Partnership
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
               The law specifies the components that the risk assessments and ERPs must address,     Public Health /   Rehab or Protection      Need / Service
                                                                       Safety
                                                                                     of Capital Stock
                                                                                                       Enhancement
               and establishes deadlines by which water systems must certify to the Environmental
               Protection Agency (EPA) the completion of the risk assessment and ERP.  2030/2035 COMPREHENSIVE PLAN? If yes, include ref:
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               Risk assessments and emergency response plans (ERPs) will not meet the state
               regulation's requirements.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Safety & Security, Infrastructure
               PROJECT #:  2022-23
                                                        EXPENDITURE SCHEDULE
                CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025      2026    UNFUNDED    TOTAL
                  PLANNING / FEASIBILITY STUDY                                                             0
                ENGINEERING & DESIGN; TESTING  450,000                                                   450,000
                    LAND & ROW ACQUISITION                                                                 0
               LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                          CONSTRUCTION         300,000                                                   300,000
                          CONTINGENCY                                                                      0
                              TOTAL    0       750,000    0        0        0        0          0        750,000
                                                         OPERATIONAL IMPACT
               OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024    2025      2026    UNFUNDED    TOTAL
                       MAINTENANCE COSTS                                                                   0
                        PERSONNEL COSTS                                                                    0
                              TOTAL    0         0        0        0        0        0          0          0
                                                          FUNDING SCHEDULE
                 CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023  2024     2025      2026    UNFUNDED    TOTAL
                          GENERAL FUND                                                                     0
                               CEDC                                                                        0
                               CCPD                                                                        0
                   PARK DEDICATION FEE FUND                                                                0
                         PUBLIC ART FUND                                                                   0
                   ROADWAY IMPACT FEE FUND                                                                 0
                  SANITARY SEWER IMPACT FEE                                                                0
                               SPDC                                                                        0
               STORMWATER UTILITY SYSTEM FUND                                                              0
                              TIRZ #1                                                                      0
                           UTILITY FUND        750,000                                                   750,000
                    WATER IMPACT FEE FUND                                                                  0
                              TOTAL    0       750,000    0        0        0        0          0        750,000
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
                CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1