CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                               WATEr



                           Funding   Total Prior
             Project number                      FY 2022   FY 2023  FY 2024   FY 2025   FY 2026   Beyond     Total
                           Source     Funding
            12-inch Water
            line along North
            Peytonville from  Funding is planned for right-of-way, engineering design and construction of a 12-inch water line along North Peytonville from
            Concho Court to  Concho Court to Southridge Lakes Parkway to increase capacity in this region and to compensate for development and growth.
            Southridge Lakes
            Parkway
            2022-36       Utility Fund       $0        $0        $0       $0    $65,000  $550,000       $0    $615,000



            Repainting of   Funding is planned to repaint the Florence Elevated Storage Tank. The paint on the water tower is from the original construction
            the Florence
            Elevated Storage  in 2005, with an expected life of 20 years. Though inspections have identified minor deterioration on the interior, these issues can
                          be addressed individually.  The interior and exterior coatings are still in good shape.
            Tank
            2022-37       Utility Fund       $0        $0        $0       $0   $400,000  $1,050,000     $0   $1,450,000



            12-inch Water
            line along East   Funding is planned for right of way, engineering design, and construction of a 12-inch water line along East Continental
            Continental   Boulevard to Breeze Way.
            Boulevard to
            Breeze Way

            2022-38       Utility Fund       $0        $0        $0       $0   $100,000  $800,000       $0    $900,000




            Repainting of the
            Dove Elevated   Funding is planned to repaint the Dove Elevated Storage Tank. The paint on the water tower was applied in 2006.
            Storage Tank


            2022-39       Utility Fund       $0        $0        $0       $0        $0   $400,000 $1,125,000  $1,525,000




            Repainting of the
            Bicentennial Park Funding is planned to repaint the Bicentennial Park Elevated Storage Tank. The paint on the water tower was applied in 2007.
            Storage Tank


            2022-40       Utility Fund       $0        $0        $0       $0        $0   $400,000 $1,200,000  $1,600,000


            Water Total                $6,338,000  $2,505,000  $6,637,000 $6,215,000  $2,937,000  $3,328,000 $2,460,000  $30,420,000