CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                     MOBILITY



                               City of Southlake FY 2022 CIP Project Status Form

                                       State Street & Frontage Road - Intersection

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   State Street and SH 114 EB Frontage Road

           PROJECT TIMELINE: Oct 2021  to  Sept 2023
           DESCRIPTION:
           Funding is planned for traffic improvements including a curbed island and new
           pavement markings at the intersection of State Street and State Highway 114. The
           improvements are based on the recommendation of a traffic study. This project will
           improve access at the intersection and enhance pedestrian safety.








                                                                     New Request  Continuation Project  Partnership
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                                  Rehab or Protection
                                                                    Public Health /
           Improve access at the intersection and enhance pedestrian safety.  Safety  of Capital Stock  Need / Service
                                                                                                   Enhancement
                                                                    2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                    Mobility Master Plan - Objective 3.1
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           Continued turn movement difficulty for traffic turning from State Highway 114 frontage
           road into State street.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Mobility, Infrastructure
           PROJECT #:  2022-10
                                                    EXPENDITURE SCHEDULE
             CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025     2026    UNFUNDED    TOTAL
              PLANNING / FEASIBILITY STUDY                                                             0
             ENGINEERING & DESIGN; TESTING                                                             0
                 LAND & ROW ACQUISITION                                                                0
           LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                      CONSTRUCTION                  140,000                                          140,000
                       CONTINGENCY                  20,000                                           20,000
                          TOTAL    0         0      160,000    0        0         0         0        160,000
                                                     OPERATIONAL IMPACT
           OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024     2025     2026    UNFUNDED    TOTAL
                   MAINTENANCE COSTS                          1,000    1,000    1,000      1,000      4,000
                    PERSONNEL COSTS                                                                    0
                          TOTAL    0         0        0       1,000    1,000    1,000      1,000      4,000
                                                      FUNDING SCHEDULE
             CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024     2025     2026    UNFUNDED     TOTAL
                      GENERAL FUND                  160,000                                          160,000
                           CEDC                                                                        0
                           CCPD                                                                        0
               PARK DEDICATION FEE FUND                                                                0
                     PUBLIC ART FUND                                                                   0
               ROADWAY IMPACT FEE FUND                                                                 0
              SANITARY SEWER IMPACT FEE                                                                0
                           SPDC                                                                        0
           STORMWATER UTILITY SYSTEM FUND                                                              0
                          TIRZ #1                                                                      0
                       UTILITY FUND                                                                    0
                 WATER IMPACT FEE FUND                                                                 0
                          TOTAL    0         0      160,000    0        0         0         0        160,000
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
            CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1

      400   FY 2022 City of Southlake  |  BUDGET BOOK
            WWW.CITYOFSOUTHLAKE.COM
   396   397   398   399   400   401   402   403   404   405   406