                                   City of Southlake FY 2022 CIP Project Status Form                                                                        114
                                                                  PEARSON LN
                                                                           FM 4091
                                   FM 1938 at West Continental Boulevard Intersection Improvements         SOUTHLAKE                   FM 1709            SOUTHLAKE
              DEPARTMENT: Public Works                                                                                                                                             N OLEN
                                                                                  M 1709
              PROJECT                                                             F FM 1709                                                         CARROLL             L  L  A
              LOCATION:   FM1938 at W. Continental Blvd Intersection  FM 1709                                                             BYRON NELSON                  B  M  I
              PROJECT TIMELINE: Oct 2021  to  Sept 2024                                DAVIS BLVD  DAVIS BLVD  PEYTONVILLE  N WHITE CHAPEL                              K
              DESCRIPTION:
               Funding is requested for right of way, new traffic signal, right turn lane, and other  UNION CHURCH RD  C CONTINENTAL L
                                                                                            N
                                                                                             E
                                                                                           I
                                                                                          N
                                                                                           T
                                                                                         O
                                                                                             N
                                                                                              T
                                                                                               A
               paving improvements to improve the alignment of this intersection based on              CONTINENTAL                         CONTINENTAL
               recommendations of a  engineering study of this intersection.  Drainage improvements
               will also be included with this project, specifically the improvement of Critical Drainage
               Structure #18.  These improvements will help alleviate current traffic backups during
               peak hours on west-bound West Continental Boulevard at FM 1938.  In addition, the  Project Location                                                    26
               project will also include landscape and irrigation improvements.                                                                           BRUMLOW
                                                                       New Request     Continuation Project     Partnership
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
               These improvements will help alleviate current traffic backups during peak hours on  Public Health /   Rehab or Protection   Need / Service
                                                                       Safety
                                                                                     of Capital Stock
                                                                                                       Enhancement
               westbound Continental Boulevard at FM 1938.
                                                                       2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                        Mobility Master Plan MT25 - Tier 3
                                                                        Storm Water Master Plan - #4 - Tier 2
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               Roadway will remain at current capacity, resulting in the continual increase in traffic  General Fund and SWUS
               congestion during peak hours.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Mobility, Infrastructure
               PROJECT #:  2022-07c
                                                        EXPENDITURE SCHEDULE
                CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025      2026    UNFUNDED    TOTAL
                  PLANNING / FEASIBILITY STUDY                                                             0
                ENGINEERING & DESIGN; TESTING  250,000                                                   250,000
                    LAND & ROW ACQUISITION     900,000                                                   900,000
               LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                          CONSTRUCTION                 2,600,000                                        2,600,000
                          CONTINGENCY          150,000  200,000                                          350,000
                              TOTAL    0      1,300,000  2,800,000  0       0        0          0       4,100,000
                                                         OPERATIONAL IMPACT
               OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024    2025      2026    UNFUNDED    TOTAL
                       MAINTENANCE COSTS                         18,000   18,000    18,000    18,000     72,000
                        PERSONNEL COSTS                                                                    0
                              TOTAL    0         0        0      18,000   18,000    18,000    18,000     72,000
                                                          FUNDING SCHEDULE
                 CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023  2024     2025      2026    UNFUNDED    TOTAL
                          GENERAL FUND  900,000  400,000  2,000,000                                     3,300,000
                               CEDC                                                                        0
                               CCPD                                                                        0
                   PARK DEDICATION FEE FUND                                                                0
                         PUBLIC ART FUND                                                                   0
                   ROADWAY IMPACT FEE FUND                                                                 0
                  SANITARY SEWER IMPACT FEE                                                                0
                               SPDC                                                                        0
               STORMWATER UTILITY SYSTEM FUND           800,000                                          800,000
                              TIRZ #1                                                                      0
                           UTILITY FUND                                                                    0
                    WATER IMPACT FEE FUND                                                                  0
                              TOTAL  900,000   400,000  2,800,000  0        0        0          0       4,100,000
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
                CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1
                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  397
                                                                                         WWW.CITYOFSOUTHLAKE.COM
   393   394   395   396   397   398   399   400   401   402   403