CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                                                             MOBILITY



                                   City of Southlake FY 2022 CIP Project Status Form

                                       N. White Chapel Blvd from Emerald Blvd to FM1709

              DEPARTMENT: Public Works
              PROJECT
              LOCATION:   N. White Chapel Blvd from Emerald Blvd to FM1709

              PROJECT TIMELINE: Oct 2021  to  Sept 2023
              DESCRIPTION:
               Funding is requested for the reconstruction of the roadway on North White Chapel
               between Emerald Boulevard and FM 1709. The roadway condition has an estimated
               Pavement Quality Index (PQI) of 59-64 and will need a pavement rehabilitation. The
               PQI values are rough estimation of the pavement's condition.








                                                                        New Request  Continuation Project  Partnership
               JUSTIFICATION:                                          Mandated /    Replacement / Major   Community
               These repairs to asphalt streets are essential maintenance. This would align with the  Public Health /   Rehab or Protection   Need / Service
                                                                       Safety
                                                                                     of Capital Stock
                                                                                                       Enhancement
               North White Chapel Boulevard widening project from Emerald to Highland without
               needing to re-mobilize. Also 99% of respondents to the most recent Citizen Survey     2030/2035 COMPREHENSIVE PLAN? If yes, include ref:
               listed maintaining local streets and roads as important.  Mobility Master
                                                                        Plan - Objective 10.6
               ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
               If the program is not funded pavement section will further deteriorate ultimately leading
               to pavement failure.
                                                                        REVENUE GENERATING? If yes, please explain:
               STRATEGIC FOCUS AREA: Mobility, Infrastructure
               PROJECT #:  2022-05
                                                        EXPENDITURE SCHEDULE
                CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025      2026    UNFUNDED    TOTAL
                  PLANNING / FEASIBILITY STUDY                                                             0
                ENGINEERING & DESIGN; TESTING  195,000                                                   195,000
                    LAND & ROW ACQUISITION                                                                 0
               LANDSCAPING,  ART,  URBAN  DESIGN                                                           0
                          CONSTRUCTION                 1,005,000                                        1,005,000
                          CONTINGENCY                                                                      0
                              TOTAL    0       195,000  1,005,000  0        0        0          0       1,200,000
                                                         OPERATIONAL IMPACT
               OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024    2025      2026    UNFUNDED    TOTAL
                       MAINTENANCE COSTS                 1,500    1,500    1,500    1,500     1,500      7,500
                        PERSONNEL COSTS                                                                    0
                              TOTAL    0         0       1,500    1,500    1,500    1,500     1,500      7,500
                                                          FUNDING SCHEDULE
                 CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023  2024     2025      2026    UNFUNDED    TOTAL
                          GENERAL FUND         200,000  1,000,000                                       1,200,000
                               CEDC                                                                        0
                               CCPD                                                                        0
                   PARK DEDICATION FEE FUND                                                                0
                         PUBLIC ART FUND                                                                   0
                   ROADWAY IMPACT FEE FUND                                                                 0
                  SANITARY SEWER IMPACT FEE                                                                0
                               SPDC                                                                        0
               STORMWATER UTILITY SYSTEM FUND                                                              0
                              TIRZ #1                                                                      0
                           UTILITY FUND                                                                    0
                    WATER IMPACT FEE FUND                                                                  0
                              TOTAL    0       200,000  1,000,000  0        0        0          0       1,200,000
               CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
                CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1
                                                                           BUDGET BOOK   |  FY 2022 City of Southlake  395
                                                                                         WWW.CITYOFSOUTHLAKE.COM
   391   392   393   394   395   396   397   398   399   400   401