Put Technology to Work
Goal 1: Ensure Availability of Information, Programs, and City Services
Objective 2: Implement New Technology
Project Performance Measure(s) City Service Team (Department)
PTW SCADA Integrator Update Treatment Production Facilities Economic Development and Capital
1.2.4 – SCADA Investment (Water)
Summary:
Milestone Estimated Actual
As the Water Department Treatment Division is Completion Completion
substantially updating its production facilities over the PBWTD Hydrogen Nov. 2020
next five years, the need for a comprehensive Supervisory Peroxide System
Control and Data Acquisition (SCADA) integration project SCADA Standards and June 2020 Dec. 2020
was identified. This project will set programming and Governance
hardware standards and modernize the Human Machine JKWTP Chemical Sept. 2022
Interface (HMI) platform utilized for all water treatment Project
operational processes. JKWTP Backwash May 2022
Improvements
Update: PBWTP Chemical Sept. 2024
SCADA standards and governance have been finalized and Clearwell and PS
are being implemented through several capital projects. Improvements
The new SCADA servers have been installed. Automated LARWPS Shared Nov. 2024
programming for the LARWPS and the PB WTP Hydrogen Operations
Peroxide System are closest to implementation and
Improvements
testing. Many of the projects have begun transitioning to
the new HMI graphics.