                                             Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                             Objective 2: Implement New Technology
                          Project                   Performance Measure(s)         City Service Team (Department)
             PTW   SCADA Integrator           Update Treatment Production Facilities  Economic Development and Capital
             1.2.4                            – SCADA                           Investment (Water)
             Summary:
                                                                       Milestone        Estimated    Actual
             As the Water Department Treatment Division is                             Completion  Completion
             substantially updating its production facilities over the   PBWTD Hydrogen   Nov. 2020
             next five years, the need for a comprehensive Supervisory   Peroxide System
             Control and Data Acquisition (SCADA) integration project   SCADA Standards and   June 2020   Dec. 2020
             was identified.  This project will set programming and   Governance
             hardware standards and modernize the Human Machine   JKWTP Chemical       Sept. 2022
             Interface (HMI) platform utilized for all water treatment   Project
             operational processes.                               JKWTP Backwash       May 2022
                                                                  Improvements
             Update:                                              PBWTP Chemical       Sept. 2024
             SCADA standards and governance have been finalized and   Clearwell and PS
             are being implemented through several capital projects.   Improvements
             The new SCADA servers have been installed. Automated   LARWPS Shared      Nov. 2024
             programming for the LARWPS and the PB WTP Hydrogen   Operations
             Peroxide System are closest to implementation and
                                                                  Improvements
             testing.  Many of the projects have begun transitioning to
             the new HMI graphics.