                           Project                 Performance Measure(s)        City Service Team (Department)
             PTW    Enterprise IT Project – Police   Project Completion     Shared Services (IT) and Neighborhood
             1.2.4   Dashboards                                             Services (Police)
             Summary:
                                                                      Milestone        Target Date     Status
             The Police Department is seeking a software solution that   Charter Development
             provides management analytics capable of connecting,   Project Planning
             manipulating, overlaying, and securing large amounts of   Design / Develop
             Police data in real‐time from multiple sources into   Implementation / Go
             interactive map‐capable dashboards for internal and   Live
             external use.                                       Project Close

             Dashboard‐Based data monitoring software will enable the   Note:
             department to detect, diagnose, report, and resolve law   This project was delayed due to the budgetary constraints
             enforcement issues. It will significantly aid executive   and impacts of COVID‐19 Pandemic.
             management with comprehensive tools for oversight. It
             will improve the department’s public reporting capacity.

             Update:
             Due to the COVID‐19 pandemic, this project was delayed
             until further notice.

                                             Put Technology to Work

                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                             Objective 2: Implement New Technology
                          Project                   Performance Measure(s)         City Service Team (Department)
             PTW  SCADA Integrator             Update Treatment Production      Economic Development and Capital
             1.2.5                             Facilities – SCADA               Investment (Water)
             Summary:
                                                                   Milestone          Estimated       Actual
             As the Water Department Treatment Division is                            Completion    Completion
             substantially updating its production facilities over   PBWTD Hydrogen Peroxide   Nov. 2020
             the next five years, the need for a comprehensive   System
             Supervisory Control and Data Acquisition (SCADA)   SCADA Standards and   June 2020
             integration project was identified.  This project will   Governance
             set programming and hardware standards and     JKWTP Chemical Project   Sept. 2022
             modernize the Human Machine Interface (HMI)    JKWTP Backwash          May 2022
             platform utilized for all water treatment operational   Improvements
             processes.                                     PBWTP Chemical Clearwell   Sept. 2024
                                                            and PS Improvements
             Update:
                                                            LARWPS Shared Operations  Nov. 2024
             Water Utilities is in the early stages of this project   Improvements
             and the estimated completion dates have been
                            st
             revised since the 1  quarter.