Page 407 - FY 2009 Proposed Budget
P. 407

Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                         Objective 3: Increase Convenience for the Customer
                           Project                 Performance Measure(s)        City Service Team (Department)
             PTW   Enterprise IT Project (FY 2019) –   Project Completion   Shared Services (Communication and
             1.3.1  City’s Website Redesign/Build                           Legislative Affairs) and Shared Services (IT)
                   Phase II
             Summary:
                                                                    Milestone         Target Date    Status
                                                                                     nd
             The City’s Website Redesign/Build project has selected   Website Design / Build   2  Qtr. FY 2019   Complete
                                                                                     rd
             and engaged the website development firm CivicLive   Implementation / Go   3  Qtr. FY 2019    Complete
             to design and build a new City Website through the   Live
             RFO process. CivicLive is providing the following   Project Close      1st Qtr. FY 2020   Complete
             services:
                    Evaluation of the City’s overall and   Note:
                    department needs                        CivicLive is recoding home and department page designs to
                    An innovative new web presence         improve site speed and will provide the recoded pages for
                    An intuitive, citizen friendly design    testing October 2019. The Project Close Target Date changed
                    A user‐friendly Web content management   from 4  quarter 2019 to 1  quarter 2020 due to schedule
                                                                 th
                                                                                 st
                    system                                  adjustments needed to address testing and implementation of
                    Building, hosting, and implementation of the   the revised code.
                    new City Website

             The first phase of the project in FY 2018 selected the
             vendor and began the design process.

             Update:
             CivicLive recoded the home and department page
                                            st
             designs to improve site speed in the 1  quarter of the
             fiscal year. The project officially closed through the IT
                                   st
             governance system in the 1  quarter as well.

             OOC and the department administrators continue
             update content and make minor improvements to the
             design through the CivicLive support help desk.