Page 412 - FY 2009 Proposed Budget
P. 412

Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                         Objective 3: Increase Convenience for the Customer
                            Project                  Performance Measure(s)      City Service Team (Department)
             PTW   Enterprise IT Project – Courtroom   Project Completion    Shared Services (IT and Municipal Court)
             1.3.6  Audio/Visual Equipment Refresh
             Summary:
                                                                      Milestone         Target Date     Status
             The project will replace the audio/visual equipment and   Charter        1/3/2020        Complete
             lighting controls in the CAR and all the five courtrooms to   Staff Report Approval   1/14/2020   Complete
             meet the specific needs of jury or bench trial settings. The   by Council
             project will also address issues with video signage and   Equipment installation   4  Qtr. FY 2020   Complete
                                                                                       th
             replace the existing signage solution.             Project Close         4  Qtr. FY 2020   Complete
                                                                                       th

             Update:
             Digital Resources, Inc. installed and configured the
             equipment in Courtrooms 1‐5 and the Court Assembly
             Room completing the last room July 6, 2020.

             Training on the new equipment was provided after the
             installation of new AV in Courtroom 5 in May 2020.

             Signage installation and Tyler Incode integration for
                                        th
             signage was completed August 17 .  Signage software
                                   th
             training was held August 18 .

             Hardware maintenance agreements were implemented
             September 2020.

             Project closed September 28, 2020.