Page 410 - FY 2009 Proposed Budget
P. 410
Put Technology to Work
Goal 1: Ensure Availability of Information, Programs, and City Services
Objective 3: Increase Convenience for the Customer
Project Performance Measure(s) City Service Team (Department)
PTW Enterprise IT Project (FY 2019) – Project Completion Shared Services (IT) and Economic
1.3.4 Arlington Permits Website Development and Capital Investment
Enhancements (Planning)
Summary:
Milestone Target Date Status
st
Arlington Permits website, arlingtonpermits.com, Project Charter 1 Qtr. FY 2019 Complete
(ap.com) is a valuable tool for customers of Planning & Development
nd
Development Services (PDS), Fire (FD), Police (PD), and Project Planning 2 Qtr. FY 2019 Complete
Code Compliance Services (CCS) to obtain information /Requirements
and request services; however, there are deficiencies Vendor SOW 2 Qtr. FY 2020 Complete
nd
and improvements that would enhance the overall Civic Portal Upgrade 2 Qtr. FY 2020 Complete
nd
customer experience. Development
Civic Portal Upgrade 3 Qtr. FY 2020 Complete
rd
PDS would like to provide customers the opportunity to Implementation / Go Live
pay fees that are not part of the default list and Enhancement Sprint – Oct. 2020 In progress
generate payment reports to aid them in reconciling Attachment and
payments. The Arlington Permits website provides Resubmittal
customers with the opportunity to pay for permits,
Enhancement Sprint ‐ Oct. 2020 In progress
request and cancel inspections, update information,
Renewals
retrieve permit and license information. Enhancement Sprint – Nov. 2020 In progress
Public Search
Update: Enhancement Sprint – Nov. 2020 In progress
Enhancement requirements were provided to the
Apply Process
Unisys vendor for review and development of a Enhancement Sprint – Dec. 2020
Statement of Work. During the Unisys review of the Payment/Shopping Cart
site, they reported operational deficiencies and Enhancement Sprint – Dec. 2020
recommended options to correct the issues identified. Reports and My Services
The option selected was to upgrade the site to Civic Project Close Jan. 2021
Portal (Smart Guide 8).
The Civic Portal upgrade passed Penetration Testing Note: Enhancement work will be delivered in Sprints,
th
and the report was delivered May 7 . The redeveloped providing new functionality in multiple Go Live events.
rd
Arlington Permits site was implemented June 3 .
Enhancement work is in progress with the following
priority areas:
1. Attachment and Resubmittal – in user testing
2. Renewals – in user testing
3. Public Search – in development
4. Apply process – enhancements prioritized
5. Payment/Shopping Cart – enhancements
prioritized
6. Reports and My Services – enhancements
prioritized
59