Page 405 - Southlake FY20 Budget
P. 405

CIP

      STORM WATER UTIlITY SYSTEM FUnD



               SPIN   Neigh-  bor-  hood       1                                  4                  3

                Comprehen-  sive Plan   Reference  Sustainability   Master Plan  Mobility   Master Plan  Storm Water   Master   Plan#1 Tier 2



               Project's   Impact to   Annual   Operating   Budget  $10,000       $10,000            $10,000



              Descrip-  tion of   Annual   Impact on   Operating   Budget  Increase in   preven-  tive and   corrective   mainte-  nance.  Increase in   preven-  tive and   corrective   mainte-  nance.  Culvert   clean-  ing and   channel   regrading.


                FY 2020   Cumula-  tive        $1,800,000                         $1,800,000         $1,800,000




                 Total                         $650,000                           $850,000           $1,750,000


                 Beyond /   Unfunded           $0                                 $0                 $0



                 FY 2024                       $0                                 $0                 $0


                 FY 2023                       $0                                 $0                 $0



                 FY 2022                       $0                                 $0                 $1,500,000



                 FY 2021                       $500,000                           $700,000           $250,000


                 FY 2020                       $0                                 $0                 $0



                 Total Prior   Funding         $150,000                           $150,000           $0





                 Description  Funding is requested   for engineering and   construction of drainage  improvements on the City's  T. W. King Pump Station #2   site. Drainage improve- ments may include design   of a detention facility and   release structure to allow   for a controlled release of   water to the existing pipe  under Rancho Laredo Trail  to the Cliffs Park. These im- provements would eliminate   the existing pond on the  property that is a mosquito  breeding ground and d





                 Project Name               Drainage   Improve-  ments at T.   W. King Pump   Station #2 to   Cliff Parks  Creekside   Drive Drain-  age Improve-  ments  Dove Creek   at North Car-  roll Avenue




                 Fund                         Storm Wa-  ter Utility   System    Storm Wa-  ter Utility   System  Storm Wa-  ter Utility   System


                 Project #                     SWUSF9                             SWUSF10            SWUSF11




    404                                        www.CityofSouthlake.com
   400   401   402   403   404   405   406   407   408   409   410