                               City of Southlake FY 2020 CIP Project Status Form

                                W. Highland St. Creek Crossing Drainage Improvements

          DEPARTMENT: Public Works
          PROJECT
          LOCATION:   Between N. White Chapel Blvd and Shady Oaks
          PROJECT TIMELINE: Oct 2019  to  Sept 2020
          DESCRIPTION:
          Funding is requested for engineering and construction of creek crossing improvements
          to replace the existing, partial steel culvert with a box culvert.









                                                                    New Request     Continuation Project  Joint Use
          JUSTIFICATION:                                            Mandated /    Replacement / Major   Community
                                                                                  Rehab or Protection
                                                                    Public Health /
          This is Critical Drainage Structure #10 which needs to be improved to ensure the     Safety     of Capital Stock     Need / Service
                                                                                                    Enhancement
          integrity of the drainage infrastructure and roadway at the creek crossing.
                                                                    Compliant with 2030/2035 Comprehensive Plan Element?

                                                                    List (incl ref #):
          ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:          COMPANION PROJECT? If yes, please explain:
          Existing drainage structure will continue to deteriorate and could result in road failure.  N/A
                                                                    REVENUE GENERATING? If yes, please explain:
          STRATEGIC FOCUS AREA: Safety & Security, Infrastructure, Mobility
                                                                     N/A
          FUND:  Storm Water Utility System
                                                    EXPENDITURE SCHEDULE
              PROJECT ELEMENT  TOTAL PRIOR  2020     2021      2022     2023      2024    UNFUNDED     TOTAL
           PLANNING / FEASIBILITY STUDY                                                                 0
               ENGINEERING & DESIGN  50                                                                 50
                           LAND                                                                         0
                         TESTING                                                                        0
                    CONSTRUCTION  100       100                                                         200
                          OTHER                                                                         0
                          TOTAL   150       100       0         0        0        0          0          250
                                                     OPERATIONAL IMPACT
              PROJECT ELEMENT  TOTAL PRIOR  2020     2021      2022     2023      2024    UNFUNDED     TOTAL
                 MAINTENANCE COSTS                    10       10        10       10         10         50
                  PERSONNEL COSTS                                                                       0
                          TOTAL    0         0        10       10        10       10         10         50
                                                      FUNDING SCHEDULE
               FUNDING SOURCE  TOTAL PRIOR  2020     2021      2022     2023      2024    UNFUNDED     TOTAL
                     GENERAL FUND                                                                       0
                           CCPD                                                                         0
                           CEDC                                                                         0
           HOTEL OCCUPANCY TAX FUND                                                                     0
            PARK DEDICATION FEE FUND                                                                    0
                   PUBLIC ART FUND                                                                      0
            ROADWAY IMPACT FEE FUND                                                                     0
            SANITARY SEWER IMPACT FEE                                                                   0
                           SPDC                                                                         0
                          SWUS    150       100                                                        250
                      UTILITY FUND                                                                      0
              WATER IMPACT FEE FUND                                                                     0
                          TOTAL   150       100       0         0        0        0          0         250
          CCPD: CRIME CONTROL & PREVENTION DISTRICT                             SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
          CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                        SWUS: STORMWATER UTILITY SYSTEM FUND
                                Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000