CIP

      STORM WATER UTIlITY SYSTEM FUnD


                                City of Southlake FY 2020 CIP Project Status Form

                                             Drainage Basin Enhancements

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   Various Locations within the City

           PROJECT TIMELINE: Oct 2019  to  Sept 2020
           DESCRIPTION:
           Funding is requested for the implementation of recommendations from revised storm
           water master plan focused on regional detention opportunities at strategic locations
           around the City. The intent of this project is to allocate funds to purchase land or
           participate with developers to incorporate regional detention into future open space.








                                                                     New Request  Continuation Project  Joint Use
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                    Public Health /      Rehab or Protection      Need / Service
           These funds allow the City to partner with developers to deliver Southlake 2030 Master  Safety  of Capital Stock  Enhancement
           Plan recommendations and those being incorporated into 2035 Master Plan.
                                                                     Compliant with 2030/2035 Comprehensive Plan Element?
                                                                    List (incl ref #):
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           City will bear full cost of creating proposed regional detention facilities or expanding  N/A
           existing facilities.
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Safety & Security, Infrastructure, Mobility
                                                                    N/A
           FUND:  Storm Water Utility System
                                                     EXPENDITURE SCHEDULE
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024    UNFUNDED     TOTAL
            PLANNING / FEASIBILITY STUDY                                                               0
                ENGINEERING & DESIGN                                                                   0
                            LAND                                                                       0
                          TESTING                                                                      0
                     CONSTRUCTION           300       100      100      100      100        100        800
                           OTHER                                                                       0
                           TOTAL   0        300       100      100      100      100        100        800
                                                     OPERATIONAL IMPACT
               PROJECT ELEMENT  TOTAL PRIOR  2020     2021     2022     2023     2024    UNFUNDED     TOTAL
                  MAINTENANCE COSTS                                                                    0
                   PERSONNEL COSTS                                                                     0
                           TOTAL   0         0        0         0        0        0         0          0
                                                      FUNDING SCHEDULE
               FUNDING SOURCE   TOTAL PRIOR  2020     2021     2022     2023     2024     UNFUNDED    TOTAL
                     GENERAL FUND                                                                      0
                           CCPD                                                                        0
                           CEDC                                                                        0
            HOTEL OCCUPANCY TAX FUND                                                                   0
             PARK DEDICATION FEE FUND                                                                  0
                    PUBLIC ART FUND                                                                    0
             ROADWAY IMPACT FEE FUND                                                                   0
             SANITARY SEWER IMPACT FEE                                                                 0
                           SPDC                                                                        0
                           SWUS             300       100      100      100      100        100        800
                       UTILITY FUND                                                                    0
               WATER IMPACT FEE FUND                                                                   0
                           TOTAL   0        300       100      100      100      100        100        800
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                           SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
           CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                      SWUS: STORMWATER UTILITY SYSTEM FUND
                                Funding is represented in thousands of dollars (000s).  Example:  3,776 = $3,776,000