                         Project                    Performance Measure(s)          City Service Team (Department)
             Core   Advanced Metering       Install 9,000 meters and MIUs in FY 2019   Economic Development and
             INF    Infrastructure                                                 Capital Investment (Water)
             2.1.1
             Summary:
                                                                     Milestone         Estimated      Actual
             The City of Arlington Water Utilities will install 9,000                 Completion   Completion
             meters and MIU’s in 2017 through an ongoing meter   Wrap up FY 2018 Installs   Sept. 2018   Sept. 2018
             replacement program and water line renewals.      Begin MUI/Meter Installs   Oct. 2018   Oct. 2018
                                                               Council Approval of    Feb. 2019
             The MIU receives input from the meter register and   Meter Replacement
             remotely sends data to a fixed base data collector,   funding
             located at one of five elevated storage tanks around   Council Approval of   Sept. 2019   Sept. 2019
             the City. Top of the hour readings and other diagnostics   Annual Meter Supply
             are instantly forwarded to the network allowing for a   Contract
             greater awareness of the distribution system and   Complete MIU/Meter    Sept. 2019   Sept. 2019
             possible on property leak conditions.  In addition, the   Installation for FY 2019
             MIU stores up to 35 days of hourly consumption,
             providing the utility with the ability to extract detailed
             usage profiles for consumer education, such as water
             conservation, and billing dispute resolution.

             Update:
             A total of 2,639 MIUs were installed during the 4th
             quarter.  The total amount installed in FY 2019 is
             10,394.