Infrastructure


                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                            Project                   Performance Measure(s)       City Service Team (Department)
             Core   Wi‐Fi System and Internet        Cost Recovery             Economic Development and Capital
             INF    Bandwidth Upgrade                Event Satisfaction Rating   Investment (Convention Center)
             1.2.4
             Summary:
                                                                     Milestone          Estimated     Status
             The Esports Stadium attendees will be using or Wi‐Fi                       Start Date
             system to communicate their experience in real‐time.    Develop Scope of Work   10/1/2018   100%
             They will be live streaming to their social media page,   Bid Project    1/1/2019      100%
             uploading photos, and downloading camera feeds and   Project Walk‐Thru   2/15/2019     100%
             tournament information via the event app/stream.    Installation Begins   1/1/2019     100%
             These bandwidth hungry activities will require an   Project Completed    2/1/2019      100%
             upgraded Wi‐Fi infrastructure to achieve.  Our current
             system is now 5 years old and is several generations
             behind the much faster and effectives systems that are
             on the market today.

             A new system would accommodate higher than 1G
             speeds and allow us to achieve greater throughput with
             higher density using new 802.11‐AC antennas.

             The Convention Center will need a 1 gigabyte fiber
             circuit to manage the public Wi‐Fi system.
             Our esports client will need a minimum of 2 ‐ 1 gigabyte
             fiber circuits to manage the tournaments.

             Update:
                   rd
             In the 3  quarter, the project is complete and working
             great.