Infrastructure
Goal 1: Plan, Manage, and Maintain Public Assets
Objective 2: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) City Service Team (Department)
Core Fire Training Upgrade Project Completion Neighborhood Services (Fire) and
INF Shared Services (AM)
1.2.2
Summary:
Milestone Estimated Actual
To more effectively deal with the growing demand Completion Completion
of Fire and EMS service in the City of Arlington, the Initial Project Feb. 2019 Feb. 2019
Arlington Fire Department has partnered with the schedule/development phase
Public Works and Transportation Department to Architect/engineer RFQ Dec. 2019
significantly update and add to the Fire Architect/engineer selection Jan. 2020
Department’s training center. The training field is process
located at 5501 Ron McAndrew Dr and has not had Architect/engineer Contract Feb. 2020
a major upgrade in over 15 years. Council approval
Architect/engineer Contract March 2020
Update: execution
th
In the 4 quarter, the project scope for this project Design May 2020
was confirmed to focus on the fire training burn Guaranteed maximum price June 2020
units and the fire training tower. A Request for sent to Council
Qualifications (RFQ) for Architects will be issued Permit review process May 2020
after architects are hired on Fire Station 1.
Construction contract July 2020
execution
Construction phase Dec. 2020
Move in Dec. 2020