                          Project                   Performance Measure(s)         City Service Team (Department)
             Core  Fire Training Upgrade       Project Completion              Neighborhood Services (Fire) and
             INF                                                               Shared Services (AM)
             1.2.2
             Summary:
                                                                   Milestone           Estimated      Actual
             To more effectively deal with the growing demand                         Completion   Completion
             of Fire and EMS service in the City of Arlington, the   Initial Project   Feb. 2019   Feb. 2019
             Arlington Fire Department has partnered with the   schedule/development phase
             Public Works and Transportation Department to   Architect/engineer RFQ   Dec. 2019
             significantly update and add to the Fire      Architect/engineer selection   Jan. 2020
             Department’s training center. The training field is   process
             located at 5501 Ron McAndrew Dr and has not had   Architect/engineer Contract   Feb. 2020
             a major upgrade in over 15 years.             Council approval
                                                           Architect/engineer Contract   March 2020
             Update:                                       execution
                   th
             In the 4  quarter, the project scope for this project   Design           May 2020
             was confirmed to focus on the fire training burn   Guaranteed maximum price   June 2020
             units and the fire training tower. A Request for   sent to Council
             Qualifications (RFQ) for Architects will be issued   Permit review process    May 2020
             after architects are hired on Fire Station 1.
                                                           Construction contract      July 2020

                                                           execution

                                                           Construction phase         Dec. 2020

                                                            Move in                   Dec. 2020