Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                         Objective 3: Increase Convenience for the Customer
                         Project                 Performance Measure(s)          City Service Team (Department)
             PTW   City’s Website            Milestone Performance          Economic Development and Capital
             1.3.1  Redesign/Build Phase II                                 Investment (IT) and Shared Services
                                                                            (Communication & Legislative Affairs)
             Summary:
                                                                     Milestone         Target Date    Status
                                                                                      nd
             The City’s Website Redesign/Build project has selected   Website Design/Build   2  Qtr. FY 2019   Complete
                                                                                      rd
             and engaged the website development firm CivicLive to   Implementation / Go   3  Qtr. FY 2019    Complete
             design and build a new City Website through the RFO   live
             process. CivicLive is providing the following services:       Project Close   1st Qtr. FY 2020   In Progress
                    Evaluation of the City’s overall and department
                    needs
                    An innovative new web presence           Note:
                    An intuitive, citizen friendly design     CivicLive is recoding home and department page designs to
                    A user‐friendly Web content management    improve site speed and will provide the recoded pages for
                    system                                     testing October 2019. The Project Close Target Date
                    Building, hosting, and implementation of the   changed from 4  quarter 2019 to 1  quarter 2020 due to
                                                                                            st
                                                                            th
                    new City Website                           schedule adjustments needed to address testing and
                                                               implementation of the revised code.
             The first phase of the project in FY 2018 selected the
             vendor and began the design process.

             Update:
             In the final quarter of the fiscal year, significant progress
             was made to refine the search feature and load time of
             the website. We also launched APRD’s Park Finder feature
             and officially shifted APRD’s website to the CivicLive
             Platform, turning off APRD’s Naturally Fun standalone
             website.

             Project closure activities are in progress.