Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                                         Objective 3: Increase Convenience for the Customer
                         Project                 Performance Measure(s)          City Service Team (Department)
             PTW   Electronic Plan Review    Turnaround time for commercial   Economic Development and Capital
             1.3.2                           construction plans within 12   Investment (IT and Planning)
                                             business days
             Summary:
                                                                     Milestone         Target Date    Status
             The implementation of an electronic plan review solution   Pre‐planning phase   Dec. 2017   Complete
             will allow multiple individuals to review plans at the same   Plan phase   Jan. 2018   Complete
             time and utilize electronic workflow thereby speeding up   RFP Release   Feb. 2018     Complete
             the approval process while continuing to meet the   Proposals Due       Apr. 2018      Complete
             Unified Development Code, City Ordinances and Zoning   Vendor Evaluations   June 2018   Complete
             requirements.                                      Contract Negotiation   July 2018    Complete

                                                                Mayor and Council    Sept. 2018     Complete
             The project includes a solution which handles the   Approval
             submission, review, and routing process for residential   Implementation   Oct. 2018   Complete
             and commercial construction including the following
                                                                Planning
             milestones:                                        Implementation/ Go   Mar. 2019      Complete
                    Perform the procurement process to evaluate,
                                                                live
                    select, and contract with a vendor for an
                                                                Go Live Support      Oct. 2019      In Progress
                    electronic plan review solution             Project Close        Oct. 2019      In Progress
                    Implement the electronic plan review solution

                    within the City Infrastructure            Note:
                                                              The project team extended the Go Live Support period on
                                           nd
             The project is planned to Go Live in 2  Quarter FY 2019.   the project from July 2019 to Oct. 2019.  This was necessary

                                                              due to the learning curve for users of the application and
             Update:
                                                              the number of issues and concerns.  There was a schedule
             The project team extended the Go Live Support period to   refinement proposed and approved.
             continue monitoring and tracking issues and concerns
             with the Electronic Plan Review solution.  The project   This schedule refinement extended the overall timeline for
             team and vendors participated in daily briefings during
                                                              the project closure from July 2019 to Oct. 2019.
             the extended Go Live Support period for a quicker
             response to issues.