                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                          Project                  Performance Measure(s)        City Service Team (Department)
             PTW   Enterprise IT Project – Court                            Economic Development and Capital
             1.1.5  Tyler Content Management                                Investment (IT) and Shared Services
                   (Laserfiche replacement)                                 (Municipal Court)
             Summary:
             The Court Tyler Content Management project will       Milestone          Target Date      Status
                                                                                    st
             oversee the planning and implementation of Tyler   Charter Development   1  Qtr. FY 2019   Complete
             Content Manager (TCM) application suite, the     Procurement          4 Qtr. FY 2019    Complete
                                                                                    th
             conversion and migration of millions of Court records to   Project Planning   1  Qtr. FY 2020   In Progress
                                                                                    st
             the new system and to retire the Courts Laserfiche   Implementation /   3  Qtr. FY 2020
                                                                                    rd
             system.                                          Document Conversion
                                                              and Migration
             Update:                                          Staff Training / Go live   4  Qtr. FY 2020
                                                                                    th
             The project team worked with the vendor to finalize the   Project Close   4  Qtr. FY 2020
                                                                                    th
             project statement of work document.  A staff report was
             developed and included in the September 24  Council
                                                 th
                                                             Notes:
             Agenda where is was reviewed and approved.  A
                                                             The remaining milestones will be updated after vendor
             purchase order has been created and submitted to the   statement of work and project schedule has been
             vendor to initiate project planning.            negotiated. This schedule refinement extended the overall

                                                             timeline for project closure.

                                             Put Technology to Work

                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                          Project                  Performance Measure(s)        City Service Team (Department)
             PTW   Enterprise IT Project – Water                            Economic Development and Capital
             1.1.6  Warehouse Inventory System                              Investment (IT and Water)
             Summary:
             The Water Department is seeking to acquire a          Milestone          Target Date      Status
             warehouse inventory management system that will   Charter Development   1  Qtr. FY 2019   Complete
                                                                                    st
             integrate with their existing Operations Management   Project Planning   2  Qtr. FY 2019   Complete
                                                                                    nd
             System (OMS) and Lawson Financials.              Procurement          4  Qtr. FY 2019   Terminated
                                                                                    th
                                                              Project Close        4  Qtr. FY 2019   Terminated
                                                                                    th
             Update:
             After CMO and departmental review, it was determined

             that the project would be cancelled and that the
             inventory management capabilities of the future ERP
             system would be evaluated and considered for use by
             the Water Department.