Page 394 - Microsoft Word - FY 2020 Adopted Budget Document
P. 394

Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                         Project                 Performance Measure(s)          City Service Team (Department)
             PTW   ERP System Plan and                                      Finance (Purchasing), Shared Services (HR),
             1.1.4  Assessment                                              and Economic Development and Capital
                                                                            Investment (IT)
             Summary:
                                                                      Milestone           Estimated    Actual
             The City of Arlington’s current ERP solution will become                    Completion  Completion
             unsupported within the next 4 years.  City staff have   Solicit RFQ for Consultant   10/1/2018   12/5/2018
             been informed that the next version of Lawson will be a   Services
             rewritten program package that will require a full‐scale   Award contract to firm for   2/19/2019   3/19/2019
             conversion as opposed to a standard upgrade/migration.   ERP consulting services
                                                              Needs Assessment Begins    6/10/2019   8/22/2019
             Through a standardized method, the Finance and Human   Present Final Assessment   10/29/2019  10/29/2019
             Resources Departments will conduct a full process and   Report to Council Committee
             needs review to determine what is the best ERP solution   Solicit RFP for an ERP Solution   12/2/2019
             for the Finance and HR staff to perform their day‐to‐day   Award contract for new ERP   9/1/2020
             operations and interactions both inside and outside of   provider
             the City.
                                                              Implementation of new      10/1/2020
                                                              solution
             Update:
             Consultant has delivered the final needs assessment
             report to the project management team (PMT) for the
             presentation to council committee in October. The PMT
             and various stakeholders also attended vendor software
             presentations in order to gain a better understanding of
             the available solutions in the marketplace. RFP
             development has begun with the consultant in
                                     st
             preparation for a December 1  release.  Project is on
             target.

































                                                             48