Enhance Regional Mobility
Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
Objective 2: Complete Construction Projects in a Timely Manner
Project Performance Measure(s) City Service Team (Department)
ERM Concrete Crack Sealing Total Aircraft Operations Economic Development and Capital
2.2.2 Investment (Aviation)
Summary:
Compliance with Grant Assurance 11, Pavement Preventative Maintenance, requires the airport to implement a
preventative maintenance program, and document all repairs, for the useful life of any pavement constructed.
Previously, all crack sealing operations were done by outside vendors. Over the past two years, the Airport has acquired
the equipment necessary to perform large‐scale repairs in‐house. Operations personnel have completed training and
perform all routine taxiway and apron crack sealing.
Update:
This project is ongoing, but the initial test is complete.
Concrete Crack Sealing
Identify and mark all cracks on the
taxiway system
Seal all cracks on Taxiway Golf, Hotel
and Juliet
Seal all cracks on Taxiway Alpha,
Bravo, Charlie, Delta, Echo and…
Identify all cracks on unleased ramp
space and entrance drives
Seal all cracks on ramps and drives
Monitor and re‐seal as needed
Update the Pavement Mangement
Program Documents
10/18 1/19 4/19 7/19 10/19
27