                                Goal 1: Enhance Economic Impact Through Development and
                            Redevelopment Efforts, Partnerships, and Investment Opportunities
                                Objective 1: Foster Development and Redevelopment in Targeted Areas
                          Project                   Performance Measure(s)        City Service Team (Department)
             IOE   EARL – East Arlington        Citizen satisfaction with overall   Shared Services (AM) and
             1.1.2  Recreation Center/Library    Library and Parks Services    Neighborhood Services (Library and
                                                                               Parks)
             Summary:
                                                                  Milestone            Estimated      Actual
             Working collaboratively with other city                                  Completion    Completion
             departments, as well as with architectural and   Initial Project        Sept. 2015   Sept. 2015
             construction management professionals, to build a   Schedule/Development Phase
             new East Arlington Recreation Center and Library   Architect/Engineer RFQ    Aug. 2015   Aug. 2015
             Complex.                                     Architect/Engineer Selection   Nov. 2015   June 2016
                                                          Process
             Update:                                      Design Development         Mar. 2018    Mar. 2018
                   th
             In the 4  quarter, the contractor has completed   Finalize construction   Fall 2018   Dec. 2018
             installation of the building foundation, paving,   documents
             structural steel and masonry walls have been   Construction contract award   Fall 2018   Feb. 2019
             erected.  This project is currently 33% complete.    Permit Process     Fall 2018    Jan. 2019

                                                          Construction begins        Fall 2018    Mar. 2019
             Phase 1, which includes building construction, is
                                                          Finalize selection of furniture   Fall 2019
             scheduled to be complete in September 2020.
                                                          and equipment
             Completion of Phase 2, which includes demolition   Recreation Center    Fall 2020
             of the existing recreation center, is scheduled for
                                                          construction complete
             February 2021.
                                                          Move In – Recreation Center    Fall 2020
                                                          Library construction complete  Fall 2020

                                                          Move In – Library          Dec. 2020