Invest in Our Economy
Goal 1: Enhance Economic Impact Through Development and
Redevelopment Efforts, Partnerships, and Investment Opportunities
Objective 1: Foster Development and Redevelopment in Targeted Areas
Project Performance Measure(s) City Service Team (Department)
IOE Redevelopment of Overall satisfaction of Construction Shared Services (AM) and
1.1.1 Texas Rangers Golf Management’s management of project Neighborhood Services (Parks)
Course Overall satisfaction of construction management
firm’s management of project
Citizen satisfaction with overall quality of parks
and recreation programs and classes
Summary:
Milestone Estimated Actual
The redevelopment of Texas Rangers Golf Course Completion Completion
is one of many redevelopment efforts in North Phase 1 construction June 2016 July 2016
Arlington. A golf course master plan recently drawings complete
approved by City Council, will include complete Phase 1 project bid Aug. 2016 Oct. 2016
renovation of the golf course, new clubhouse Phase 1 construction begins Nov. 2016 Jan. 2017
and maintenance building, expanded driving Phase 2 construction June 2017 June 2017
range and a practice facility. The golf course drawings complete
improvements will provide a high‐quality playing Phase 2 project bid July 2017 Aug. 2017
experience at an affordable price point for Phase 2 construction Sept. 2017 Sept. 2017
Arlington residents while providing another
contract award
destination for visitors to the Entertainment Phase 2 construction begins Sept. 2017 Nov. 2017
District. Phase 3 construction Oct. 2017 Oct. 2017
drawings complete
Update:
th
During the 4 quarter, Phase 3, Clubhouse Phase 1 construction Nov. 2017 Oct. 2017
construction included completion of the complete
Phase 3 project bid Nov. 2017 Nov. 2017
basement, paving, structural steel and wood
Phase 3 construction Dec. 2017 Dec. 2017
framing. The Clubhouse project is currently 58%
contract award
complete.
Phase 3 construction begins Mar. 2018 Mar. 2018
Due to continuing weather delays and finalizing Phase 2 construction Aug. 2018 Apr. 2019
design changes, the Clubhouse opening is now complete
scheduled for June 2020. Golf course grand opening Sept. 2018 May 2019
Phase 3 construction June 2020
complete
Overall project completion June 2020