Page 380 - Microsoft Word - FY 2020 Adopted Budget Document
P. 380

Invest in Our Economy


                                Goal 1: Enhance Economic Impact Through Development and
                            Redevelopment Efforts, Partnerships, and Investment Opportunities
                                Objective 1: Foster Development and Redevelopment in Targeted Areas
                       Project                     Performance Measure(s)           City Service Team (Department)
             IOE   Southeast Recreation     Overall satisfaction of Construction   Shared Services (AM) and
             1.1.4  Center                 Management’s management of project      Neighborhood Services (Parks)
                                           Overall satisfaction of construction
                                           management firm’s management of project
                                           Citizen satisfaction with overall quality of
                                           parks and recreation programs and classes
             Summary:
                                                                  Milestone           Estimated       Actual
             Working collaboratively with other city                                  Completion    Completion
             departments, as well as with architectural and   Initial Project        Jan. 2017    Jan. 2017
             construction management professionals, to build a   Schedule/Development Phase
             new Southeast Arlington Recreation Center.   Architect/Engineer RFQ     Feb. 2017    Feb. 2017
                                                          Architect/Engineer Selection   Feb. 2017   Mar. 2017
             Update:                                      Process
                   th
             In the 4  quarter, foundation has been completed,   Design Development   June 2017   June 2018
             structural steel has been erected, masonry walls   Finalize construction   Summer 2018  Dec. 2018
             have been erected, roof decking is in progress, the   documents
             skate park has been completed. This project is   Construction contract award   Fall 2018   Dec. 2018
             currently 36% complete.                      Permit Process             Fall 2018    Jan. 2019

                                                          Construction begins        Fall 2018    Feb. 2019
                                                          Finalize selection of furniture   Fall 2019
                                                          and equipment
                                                          Construction complete      Summer 2020
                                                          Move In                    Fall 2020