CIP AND CAPITAL PROJECTS FUNDS


                   Justification:  The  current  condition  of  the  Public  Works  yard  pavement  area  is  in
                   complete  disrepair  and  in  need  of  a  complete  replacement.    In  addition,  the  recent
                   expansion of the fleet maintenance building has created a need to optimize parking.

                   Operating Impact:  This project is being funded by the 2024 Certificate of Obligations
                   issued in September 2024.


                         FY2024-2025 ECONOMIC DEVELOPMENT PROJECTS DISCUSSION


               ❖  Description:  Food Business Park Project, $500,000
                   This EDC project will provide for the construction of a food business park at Capp Smith
                   Park.  The site is planned to include a small entertainment stage with associated parking.
                   The project began back in FY22-23 and is anticipated to be completed during FY24-25
                   with a total project expense of $500,000.

                   Justification: This project was designed to spur economic development activity in the
                   city and surrounding region to help rebound from the impact of COVID-19.  In addition,
                   the private ownership of available parcels has caused the small restaurant entrepreneurs
                   to seek other options outside of the City due to cost of real estate.  The site will allow for
                   mobile restaurants to support and promote economic activity within the City of Watauga
                   with the objective to give restaurant owners the opportunity to build up a clientele in the
                   Northeast Texas Mid-Cities area with minimal start-up costs.

                   Operating Impact: Funds are provided by the 2020 Certificates of Obligation proceeds.
                   The  City  anticipates  the  impact  of  the  operating  budget  for  maintenance  of  the  food
                   business park to be approximately $3,000 per year after completion.

                                   FY2024-25 STREETS/SIDEWALKS DISCUSSION


               ❖  Description: FY2024-2025 Street Overlay, $800,000
                   This project provides for the curb and gutter, subgrade, milling, and asphalt overlay for 7-
                   8 streets annually.

                   Justification: The existing asphalt  pavement for
                   certain  streets  is  deteriorating.    The  asphalt
                   overlay will provide an improved riding surface and
                   will  extend  the  life  of  the  roadways  and  will
                   enhance the appearance of the streets.

                   Operating  Impact:  The  street  program  is  cash
                   funded by a transfer from the General Fund to the
                   Capital Projects fund.