Page 430 - FY 2025 Adopted Operating Budget and Business Plan
P. 430

Return to Table of Contents




                                               Leverage Technology

                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                           Project                  Performance Measure(s)               Department(s)
             LT    Kronos Replacement            Project Completion            Information Technology, Human
             1.1.3                                                             Resources, and Finance
             Summary:
                                                                    Milestone        Target Date      Status
             The current version of Kronos is approaching end of life.    Consulting Services   3  Qtr. FY 2024   Complete
                                                                                    rd
             The replacement product being considered is Workday   SOW
                                                                                    rd
             Time Tracking. The Workday Time Tracking will provide a   Workday Time   3  Qtr. FY 2024   Complete
             standardized workforce management system.          Tracking
                                                                Procurement
             Update:                                            Project Kick Off   4  Qtr. FY 2024   Complete
                                                                                    th
             The Project Kick Off meeting with Workday consulting   Planning       4  Qtr. FY 2024   Complete
                                                                                    th
             partner, Active Cyber, was held on August 21, 2024.    Architect/Configure   1  Qtr. FY 2025   In progress
                                                                                    st
                                                                                    nd
                                                                Testing            2  Qtr. FY 2025
             The Time Tracking, Payroll, and Absence project    Go Live/Deployment   2  Qtr. FY 2025
                                                                                    nd
             workbooks have been completed. These workbooks                         nd
                                                                Change             2  Qtr. FY 2025
             provide the roadmap for configuring Workday modules.   Management/
             The project team is working on the configuration and   Training
             developing test plans.                                                 nd
                                                                Post Go Live Support   2  Qtr. FY 2025
                                                                                    nd
                                                                Project Close      2  Qtr. FY 2025
             The Workday Time Tracking System procurement of the
             new time clocks was approved by City Council. The time
                                                               Milestones updated based on partner vendor Scope of
             clock partner vendor is engaged and working on the
                                                               Work (SOW).
             Workday integrations for the time clocks.