Page 428 - FY 2025 Adopted Operating Budget and Business Plan
P. 428

Return to Table of Contents




                                               Leverage Technology

                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                           Project                  Performance Measure(s)               Department(s)
             LT    Phase 2 ERP System            Project Completion            Information Technology, Human
             1.1.1  Implementation – HCM & Payroll                             Resources, and Finance
                   Modules
             Summary:
                                                                    Milestone        Target Date      Status
             In FY 2020, the City issued an RFP for a new Enterprise   Business Process   2nd Qtr. FY   Complete
             Resource Planning (ERP) system.  Phase 1 (Finance)   Alignment        2022
             Implementation of the new system started/was       Planning           3rd Qtr. FY 2022  Complete
             completed in FY 2021.  Phase 3 (Recruiting) is scheduled   Architect   3rd Qtr. FY 2022  Complete
             to complete in 2024.  Schedule for implementation of   Configure/Prototype   1st Qtr. FY 2023   Complete
             Adaptive Planning (Budget) is pending.             E2E Testing        2nd Qtr. FY     Complete
                                                                                   2023
             Phase 2 – Human Capital Management and Payroll,    Parallel Testing   3rd Qtr. FY 2023  Complete
             (1/03/2022 – 10/31/2023) – Includes HCM, Benefits,   Integration      3rd Qtr. FY 2023  Complete
             Compensation, Absence, and Payroll.
                                                                Reporting          3rd Qtr. FY 2023  Complete
                                                                Change Order       3rd Qtr. FY 2023  Complete
             Update:                                            Dress Rehearsal    4  Qtr. FY 2023   Complete
                                                                                    th
             Workday Phase 2 is complete including training, job aids,   Go Live/Deployment   4  Qtr. FY 2023   Complete
                                                                                    th
             post go live support, and project acceptance                           st
             documentation.                                     Change             1  Qtr. FY 2024   Complete
                                                                Management/
                                                                Training
             The project phase is completed and closed.
                                                                                    st
                                                                Post Go Live Support   1  Qtr. FY 2024   Complete
                                                                                    st
                                                                Phase 2 Project    1  Qtr. FY 2024   Complete
                                                                Close