                                                    Infrastructure


                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                        Project                     Performance Measure(s)           City Service Team (Department)
             Core    Tierra Verde Golf Course     Overall satisfaction of project management   Shared Services (AM) and
             INF    / Ventana Grille –       Project completion on time and at budget   Neighborhood Services (Parks)
             1.2.3   Geothermal HVAC         Citizen satisfaction with overall quality of
                    System                   parks and recreation programs and classes
             Summary:
                                                                     Milestone          Estimated     Actual
             The existing geothermal HVAC system currently                              Completion   Completion
             operating at Tierra Verde Golf Clubhouse and Ventana   Identify location of existing   Jan. 2019   Feb. 2019
             Grille is beginning to fail causing insufficient cooling   piping and thermal wells
             throughout the facility. Asset Management will   RFQ process for Mechanical   Feb. 2019   May 2019
             collaborate with the Parks Department to determine   Engineering firm
             the best cost‐effective approach to either improve the   Engineering firm selection   Feb. 2019   June 2019
             existing geothermal system or recommend          process
             replacement with a conventional HVAC system. As part   Council approval of   Aug. 2019   Aug. 2019
             of the project, temporary temperature control
                                                              Engineering firm
             measures will be considered as needed.           Design, including review of   Fall 2019   Jan. 2020
                                                              recommended options
             The time frame for the request for qualification for   Bidding Process    Spring 2020   Mar. 2020
             mechanical engineer was revised from February 2019
                                                              Permit review process    TBD 2020     Apr. 2020
             to May of 2019.  Additional time was needed to
                                                              Contractor Council approval  TBD 2020   Apr. 2020
             complete a feasibility study to define the scope of   Construction phase   Sept. 2020   Oct. 2020
             work.

             Update:
                                          st
             This project was completed in the 1  quarter of FY
             2021.



































                                                             114