Infrastructure
Goal 1: Plan, Manage, and Maintain Public Assets
Objective 2: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) City Service Team (Department)
Core Fire Training Upgrade Overall satisfaction of project management Shared Services (AM) and
INF Project completion on time and at budget Neighborhood Services (Fire)
1.2.2
Summary:
Milestone Estimated Actual
To more effectively deal with the growing demand of Completion Completion
Fire and EMS service in the City of Arlington, the Initial Project Feb. 2019 Feb. 2019
Arlington Fire Department plans to make improvements schedule/development
at the Fire Department’s training center. The training phase
field is located at 5501 Ron McAndrew Dr. and has not Architect/engineer RFQ Dec. 2019 Dec. 2019
had significant improvements in over 15 years. Architect/engineer Jan. 2020 Jan. 2020
selection process
Update:
Architect/engineer Feb. 2020 Feb. 2020
Project is pending as the scope of work is determined. Contract Council approval
No update at this time. Architect/engineer Mar. 2020 Mar. 2020
Contract execution
Design TBD
Guaranteed maximum TBD
price sent to Council
Permit review process TBD
Construction contract TBD
execution
Construction phase TBD
Move in TBD