                                             Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                             Project                   Performance Measure(s)      City Service Team (Department)
             PTW    Enterprise IT Project (FY 2019) –   Project Completion      Shared Services (IT and Municipal
             1.1.4   Tyler Content Management                                   Court)
                    (Laserfiche replacement)
             Summary:
                                                                   Milestone          Target Date     Status
             The Court Tyler Content Management project will   Charter Development   1  Qtr. FY 2019   Complete
                                                                                     st
             oversee the planning and implementation of Tyler   Staff Report Approval by   4  Qtr. FY 2019    Complete
                                                                                     th
             Content Manager (TCM) application suite, the    Council
             conversion and migration of millions of Court records   Procurement    4  Qtr. FY 2019    Complete
                                                                                     th
             to the new system and to retire the Courts Laserfiche   Project Planning   1  Qtr. FY 2020   In Progress
                                                                                     st
             system.                                         System implementation   1st Qtr. FY 2022   In Progress
                                                             and configuration
             Update:                                         Document Conversion    2nd Qtr. FY 2022   In Progress
                       th
             During the 4  quarter, Tyler continued a lengthy work   and Migration
             effort towards remediating documented issues.  Two
                                                             Staff Training / Go Live   2nd Qtr. FY 2022
             software upgrades later, Tyler has resolved a critical   Project Close   2nd Qtr. FY 2022
             issue related to PDF document recall and displaying
             within the TCM application.  Three less critical but
                                                            Notes:
             important issues remain that require the vendor to
                                                            This schedule refinement extended the overall timeline to
             develop software code fixes to resolve.  Tyler has   achieve project closure.
             committed to delivering corrected software by early
             2  quarter FY 2022.  Work to perform a smaller
              nd
             document conversion was started but had to be
             stopped when the process tried to relocate previously
             converted documents from file storage back into the
             database, eventually running out of space.  After
             extensive project team discussion, it was mutually
             determined that the best approach to move forward,
             was to cleanse all documents out of the TCM system
             and redo the proof‐of‐concept document conversions.
             The proof‐of‐concept redo will be performed during
             the 1  quarter FY 2022.