Enhance Regional Mobility


                          Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
                                    Objective 2: Complete Construction Projects in a Timely Manner
                       Project                   Performance Measure(s)           City Service Team (Department)
             ERM   Street Rebuild Projects   Overall satisfaction with the management   Economic Development and Capital
             2.2.1                       of traffic flow during peak hours     Investment (PWT)
             Summary:
                                                                 Roadway Capital Improvements Project   Lane
             Capital street projects are funded with Street Bonds                                       Miles
             and are funded through inclusion in the annual   2018 Residential Rebuild (Daniel Drive)    1.4
             capital budget.                                 2018 Residential Rebuild (Miriam Lane)      1.5
                                                             Avenue E (SH360 to Great Southwest Parkway)   3.9
             The projects listed to the right are expected to   Bowman Springs Road (IH20 to Enchanted Bay   1.2
             receive construction funds in March 2020. The   Blvd)
             projects listed below include carry‐over projects from   Poly Webb Road (Pleasant Ridge Road to   1.0
             FY 2019 that have not completed construction, as   Shorewood Drive
             well as the planned FY 2020 projects. Project   Turner Warnell Road (Matlock Road to Cooper   6.2
             milestones listed in the table will be updated as they   Street)
             occur during the year.
                                                             2020 CDBG Vanderbilt & Hanover              1.0

             Update:
                                                           Prior to advertisement for bids for the 2018 Residential Rebuild
             Due to projected budget impacts resulting from   Project, PWT followed the new protocol for Solicitation and
             COVID‐19, funding for the projects expected to   MWBE Utilization Approval through the Purchasing Division. The
             receive construction funds in March were released   project was repackaged into two projects (Daniel Drive and
                     th
             on July 29 .
                                                           Miriam Lane) and advertised for bid in September.


                    Roadway Capital Improvement Project       Estimated    Actual Bid   Estimated     Actual
                                                               Bid Date      Date      Completion   Completion
               Abram Street (Cooper Street to Collins Street)   Feb. 2018   Feb. 2018   Mar. 2020
               Eden Road (US287 to Calender Road)            June 2018    Aug. 2019    July 2021
               2017 Residential Rebuild Phase 2              Mar. 2019    Feb. 2019    Mar. 2020   Sept. 2020
               2019 CDBG Residential Rebuild                 Mar. 2019    Feb. 2019    Nov. 2019   Apr. 2020
               Collins Street (IH20 to Mayfield Road)        Apr. 2019    Feb. 2019    Dec. 2019   May 2020
               Calender Road (Harris Road to Eden Road)      Apr. 2019    May 2020     Nov. 2021
               Avenue H (SH360 to Great Southwest Parkway)   May 2019     Sept. 2019   June 2021
               Harris Road (Calender Road to Cooper Street)   May 2019
               Collins Street (Pioneer Parkway to Park Row Drive)   June 2019   July 2019   May 2021
               2019 CDBG Residential Rebuild (Kimberly Drive)   June 2019   May 2019   Mar. 2020   May 2020
               2018 Residential Rebuild (Daniel Drive)       May 2020     Oct. 2020    Aug. 2021
               2018 Residential Rebuild (Miriam Lane)        May 2020     Oct. 2020    Nov. 2021
               2020 CDBG Residential Rebuild (Vanderbilt Drive &   June 2020   Sept. 2020   Nov. 2021
               Hanover Drive)
               Bowman Springs Road (IH20 to Enchanted Bay Blvd.)   June 2020
               Turner Warnell Road (Matlock Road to Cooper Street)  Aug. 2020
               Avenue E (SH 360 to Great Southwest Parkway)   Aug. 2020